Baseline in Master and Sub-Projects with MS PROJECT 2016

Hi, we all know what the Baseline is. But where is the right place to make it, if we have a Project which is Subproject of Master Project. I will show you where with MS PROJECT 2016. First of all … Continue reading

Posted in MICROSOFT PROJECT, Microsoft Project 2013, MS PROJECT 2016, PMI, PRoject Management | Tagged , , | Leave a comment

Update the task as 100% without changing work hours automatically in MS PROJECT 2016 – is it possible?

Hi, I’ve got very good question from one of my Blog Readers: “How can I do to update the task as 100% but without changing work hours automatically? Because I want to know that my team is more efficient than … Continue reading

Posted in MICROSOFT PROJECT, Microsoft Project 2013, Micsrosoft Project 2016, MS PROJECT 2010, MS PROJECT 2016 | Tagged , , | Leave a comment

%Complete, %Work Complete, and Project without Resources with MS PROJECT 2016!

Hi, I’ve got a question from one of my Blog Readers: “Please clarify the following: I have created a Sample project in MS Project 2013, with tasks and assigned duration  with required predecessors.I have base lined the plan and started … Continue reading

Posted in Microsoft Project 2013, MS PROJECT 2010, MS PROJECT 2016, PMI, PRoject Management | Tagged , , , , | Leave a comment

New Tasks and saved Baseline in MS PRIOJECT 2016

  Hi, I have a reader who is novice in MS PROJECT 2016, and he has a problem; “Hi, I hope you are in good health. I have some quires about cost tracking in MS Project. I had previously saved … Continue reading

Posted in Microsoft Project 2013, Micsrosoft Project 2016, MS PROJECT 2016, PMI, PRoject Management | Tagged , , , | 1 Comment