Tag Archives: Micorosft Project 2019 – Tasks

Resources with dynamic workload in MS PROJECT 2019

Hi, today I will show you how to deal with a problem which you will face, almost, in every Project. And that is: “Resources which are leaving Project, and coming back after some time to perform the same Task!”. Let’s … Continue reading

Posted in MICROSOFT PROJECT, MICROSOFT PROJECT 2019, PMI, PRoject Management | Tagged , , | Leave a comment

Creating Fixed Duration Task using Task form in MS Project 2019

Hello, today I’m going to show you how to use Task Form for creating Tasks from the scratch using MS PROJECT 2019! First of all, let me crate two brand new Project: OK. I need John and Mary as Resources, … Continue reading

Posted in MICROSOFT PROJECT 2019 | Tagged , , | Leave a comment

How to link Tasks with recurring Tasks in MS PROJECT 2019

Hi, suppose that every Monday you have a meeting with your project team. And after that you are going back to your regular project Tasks. For that case you will have to create recurring in Project 2019 Task for meeting … Continue reading

Posted in MICROSOFT PROJECT, MICROSOFT PROJECT 2019 | Tagged | Leave a comment

Rollup field in MS PROJECT 2019

Hi, today I’m going to explain purpose of the Rollup for Tasks in MS PROJECT 2019! First I will create very simple Project: As you can see, there is one Summary Task (Task S), two Sub-summary Tasks (Tasks S1 and … Continue reading

Posted in MS PROJECT 2019 | Tagged | Leave a comment

Actual duration and Actual start “problem” in MS PROJECT 2019

Hi, I have a question from blog reader: “Hi Nenad, I would like to track the progress in the following scenario:Task A: 3,5 d durationTask B: 3 d duration with a constraint FS with task AProgress: Say that Task A … Continue reading

Posted in MICROSOFT PROJECT 2019 | Tagged , | Leave a comment