-
Recent Posts
Archives
Categories
Blogroll
Category Archives: MS PROJECT 2010
Milestone and Finish to Finish relationship in MS PROJECT 2016
Hi, I’ve got an interesting question form one of my blog reader. He’s got a problem. I will show you what kind of Problem does he has with MS PROJECT 2016! Firs I will create new Project: Everything looks perfect. … Continue reading
Task type and Resource Calendars in MS PROJECT 2016
Hi, I’ve got very specific question from one of my blog Reader, and I’m going to answer this step by step using MS PROJECT 2016 Here is Scenario from my Blog Reader (Italic font represent his questions, and Normal font represent … Continue reading
Task 0 in MS PROJECT 2016
Hi, This post will be short, but very useful. I have a question from one of my Blog Readers: “Hi Nenad,I discovered hat my task number usually starts from 1 instead of 0.Kindly assist on this.” I will show … Continue reading
Work assigned to Tasks vs. Work assigned to resources and Task Types in MS PROJECT 2016
Hi. Today I will show you what happens when you put work in hours to the Tasks, and then assign Resources to the Task, using MS PROJECT 2016. Firs II ‘m going to create new Project: As you can see, … Continue reading
Duration, Work and Units relation with no Resources assigned
Hi, I have a question from my Blog Reader: “If you are not using resources in the scheduling, should you always just leave the Effort Driven box unchecked?” I will answer this question right away: “”It doesn’t matter. Effort driven … Continue reading
How to calculate work, and then fix it in IN MS PROJECT 2016
Hi, friend of mine has a Specific problem. He wants MS PROJECT. I will show you this problem with MS PROJECT 2016! Project has one Task: Resources are: As you can see there are Workers with 800% capacity, Laborers with … Continue reading
How to delete all dependencies for one Task in MS PROJECT 2016
Hi, for the last post in this year I choose to show you a very simple Trick. What if you have one Task with multiple Tasks dependencies, and, for some reason you want to remove those dependencies in one step. … Continue reading
Replacing Generic Resources with Human Resources and overallocation!
Hi, I’ve got a question from one of my Blog readers: “When I assign Generic Resource to a Task and then replace it with human resource how can I decrease availability of generic Resource?” I will show you that in … Continue reading
“Keep task on nearest working day when changing to automatically scheduled mode” option in MS PROJECT 2016
Hi, a lot of my Blog readers asked me about “keep task on nearest working day when changing to automatically scheduled mode” option in MS PROJECT! I will show you what is it, and how does it work in MS … Continue reading
Material Resources with new Resource assigned to the Tasks in MS PROJECT 2016
Hi, today I’m going to show you what is going to happen with Material resources when you assign additional Work resources to the Task which has already started and have some actuals. I will use Microsoft Project 2016! First I’m … Continue reading