How to calculate work, and then fix it in IN MS PROJECT 2016

Hi,

friend of mine has a Specific problem. He wants MS PROJECT. I will show you this problem with MS PROJECT 2016!

Project has one Task:

image

Resources are:

image

As you can see there are Workers with 800% capacity, Laborers with 200% capacity, and Crane and Concrete mixer with 100% capacity.

Workers are supposed to work 300 hours, Laborers 50 hours, Crane 10 hours, and Concrete mixer  20 hours.

Duration of this Task should be calculated by MS PROJECT using workers. SO I will assign Workers to the Task, and I will put 800% for Units, and 300 hours to get Duration:

image

and I will get:

image

Now I want to assign remaining Resources like this:

  • Laborers 200% 50 hours
  • Crane 100 % 10 hours
  • Concrete mixer 100% 20 hours

but I want to spread the work during all days of Duration.

First I will assign them as-is:

image

and I will get:

image

As you can see, I didn’t get what I wanted. Laborers will work only fist four days, Crane only first two days, and Concrete mixer only first three days. What Can I do? Well, before assign those resources I will switch Task to the Fixed duration mode:

image 

Now I am going to assign those resources in the same way:

image

Finally, I will get:

image

As you can see, all resources are used all days (Duration days). Of course they will not spend same amount of hours, as expected.

To conclude, if you want to calculate duration according to one Resource, and then spread the work through duration for rest Resources, follow this steps:

  1. Use fixed units or Fixed work and assign first resource. Duration will be calculated.
  2. Switch the Task to Fixed Duration Type
  3. Assign remaining resources to Task.

Regards.

Unknown's avatar

About Nenad Trajkovski

Location: Zagreb, Croatia Occupation: Project Manager Interests: Project Management and MS PROJECT He was born in Zagreb, Croatia at 1963. After completing his college he started working on projects in different business areas (banking, manufacturing, automotive industry, distribution, oil companies, etc.) developing and implementing ERP systems into different companies. He has got a lot of experience working with people in different business processes and also possesses great knowledge in information technologies and financial services. Today he works as a business consultant, adn Project Manager in PERPETUUM MOBILE d.o.o. Zagreb. He is a regular lecturer for Project Management in MS Innovation Center in Varaždin, Logosoft Sarajevo in Bosnia and Herzegovina and SEAVUS GROUP in Skopje Macedonia. He was named the best lecturer of WINDAYS 2008 while his lecture was also voted as the best. In addition, he was in TOP 10 lecturers at the MS SINERGY 2009 and MS VISIA 2009, 2010. Shares first place as the best lecturer of KulenDays 2009 and 2010 and PMI Conference 2009 in Zagreb. He is also a regular lecturer in the MS Community. He is a Certified Accountant and a PMP (Project Manager Professional) and a PMI-RMP (Risk Manager Professional), MCP, MCT, and Microsoft Certified Technical Specialist - Microsoft Project 2010. From 01.01.2012 awarded with MVP (Microsoft Most Valuable Proffesional - Microsoft Project)!
This entry was posted in Microsoft Project 2013, Micsrosoft Project 2016, MS PROJECT 2010, PMI, PRoject Management and tagged . Bookmark the permalink.

Leave a comment