Extended Duration with Fixed working hours–MS PROJECT 2016

Hi,

I have very interesting question from one of my Blog readers:

“Hi Nenad,

I would appreciate if you could advise on the following two  topics:

1. How to handle the situation when a task is delayed due to some unforeseen circumstances, but the actual work performed by several assigned resources remains unchanged

For example:

Task A  = 3d with Resources R1 and R2 assigned at 100% each. Work is 48h . R1 work = 24h, R2 work = 24h

Let’s assume that this task is delayed 2 days. So we enter the  Actual Duration of  5d or instead enter the Actual Finish day for the task to correspond to day 5.

So how and  where should we enter value  for each resource so the 5d task is 100% and the actual work for each resource is planned 24h?

Note: Please explain this for each task type!

2. Same situation as above, but the Actual Duration of the task is shorter than planned, while the Actual Works for resources are same as planned.”

OK! Let me show you that with MS PROJECT 2016!

First I am going to create brand new Project with one Task with 3 days Duration:

image

No I am going to create two resources:

image

and finally, I’m going to assign those resources to Task:

image

Now I’m going to switch to the Task Usage View:

image

For my example, I added three more Columns: Actual work, Remaining work, and Task Type.

I will now change duration from 3 to 5 days, for:

Fixed Units and Fixed Duration

image

As you can see, Work is extended as well, from 24 hours to 40 hours per Resource. But, if I click on the Yellow sign, I can choose:

image

In this case I will get what I want, e.g. work will remain the same for each Resource, but they will work less per day:

image

Fixed Work

If I change Duration on that Task Type, I will not have to choose anything to get the same result, because by default, Fixed work means that if I change Duration, work will remain the same (e.g. 24 hours per Resource), and it will be spread among 5 days (e.g. each Resource will have to work less per day on that Task).

The same thing will happen if I short Duration. But, in that case for Fixed Units, and Fixed Duration I will have to choose that I want to Increase the hours work per day, and with fixed Work it will be automatically done for me.

Hope this helps.

Regards!

Unknown's avatar

About Nenad Trajkovski

Location: Zagreb, Croatia Occupation: Project Manager Interests: Project Management and MS PROJECT He was born in Zagreb, Croatia at 1963. After completing his college he started working on projects in different business areas (banking, manufacturing, automotive industry, distribution, oil companies, etc.) developing and implementing ERP systems into different companies. He has got a lot of experience working with people in different business processes and also possesses great knowledge in information technologies and financial services. Today he works as a business consultant, adn Project Manager in PERPETUUM MOBILE d.o.o. Zagreb. He is a regular lecturer for Project Management in MS Innovation Center in Varaždin, Logosoft Sarajevo in Bosnia and Herzegovina and SEAVUS GROUP in Skopje Macedonia. He was named the best lecturer of WINDAYS 2008 while his lecture was also voted as the best. In addition, he was in TOP 10 lecturers at the MS SINERGY 2009 and MS VISIA 2009, 2010. Shares first place as the best lecturer of KulenDays 2009 and 2010 and PMI Conference 2009 in Zagreb. He is also a regular lecturer in the MS Community. He is a Certified Accountant and a PMP (Project Manager Professional) and a PMI-RMP (Risk Manager Professional), MCP, MCT, and Microsoft Certified Technical Specialist - Microsoft Project 2010. From 01.01.2012 awarded with MVP (Microsoft Most Valuable Proffesional - Microsoft Project)!
This entry was posted in MICROSOFT PROJECT, Microsoft Project 2013, MS PROJECT 2016, PMI, PRoject Management and tagged , . Bookmark the permalink.

2 Responses to Extended Duration with Fixed working hours–MS PROJECT 2016

  1. Alex Shafir's avatar Alex Shafir says:

    Hi Nenad,

    I wonder if this is a bug in MS Project 2013.
    Here what I did:
    1. Created a 3-day fixed units, non-effort-driven task
    2. Assigned one resource at 100% capacity
    3. Changed Duration from 3d to 5d
    4. Chose the option “Decrease hours resources work per day but keep the same amount of work” so that scheduled Work remained unchanged

    In response Project :
    a). changed Peak Units to 60%. Which is correct. But it also changed the Assignment Units to 60%. And I don’t understand why?!!!
    b). Project made the task to be an effort-driven. Why?

    Thank you,
    Alex Shafir

    • Nenad Trajkovski's avatar Nenad Trajkovski says:

      Read this: https://ntrajkovski.com/2016/07/18/why-is-my-task-type-changed-from-non-effort-driven-to-effort-driven-automatically-in-ms-project-2016/

Leave a comment