Task start date depending on predecessors competition–is that possible in MS PROJECT?

Hi,

I’ve got interesting question from on of my blog readers and it is: “Let’s say that you have Task 1 and Task 2. Task 2 can start when 25% of Task 1 is completed, and Task 1 can continue after task 2 is completed. Is there an option to make such relation and such split (not manually)?”

I will show you that in MS PROJECT 2019!

image

This is classis Finish to Start relationship. If I want Task 2 to start after 25% of Task 1 is completed, it is not possible. Why? MS PROJECT calculate successor’s Start date depending on many things like Calendars, Exception dates, Task relationship type (for example, Finish to Finish is not the same as Finish to start), but it does not calculate successor’s start date depending on predecessors completeness. But you can make that Start date of Task 2 is 25% after Task 1 start date like this:

SNAGHTML3f52df37

Notice that I put 4 days for Task 1 duration just to show you that Task 2 will start 1 day latter then Task 1 (which is 25% of duration of Task 1).

If you insist on Finish to Start relationship you can do the following:

SNAGHTML3f551263

So Task 2 will start 75% before Task 1 is finished which is 3 days, e.g. 1 day after Task 1 start date.

BUT! This has nothing to do with % completeness. In both pictures above Task 2 should start 1 day after Task 1 should been started, no matter if it was started or not!

The other question was is it possible that Task 1 can continue after Task 2 is finished? It means that Predecessor can be worked on after successor is completed! And here I can’t show you example because it is just impossible! First , it is impossible to establish two or more different relations between two Tasks, and second it is impossible to control work on one Task depending on completeness of the other Tasks!

Regards!

Unknown's avatar

About Nenad Trajkovski

Location: Zagreb, Croatia Occupation: Project Manager Interests: Project Management and MS PROJECT He was born in Zagreb, Croatia at 1963. After completing his college he started working on projects in different business areas (banking, manufacturing, automotive industry, distribution, oil companies, etc.) developing and implementing ERP systems into different companies. He has got a lot of experience working with people in different business processes and also possesses great knowledge in information technologies and financial services. Today he works as a business consultant, adn Project Manager in PERPETUUM MOBILE d.o.o. Zagreb. He is a regular lecturer for Project Management in MS Innovation Center in Varaždin, Logosoft Sarajevo in Bosnia and Herzegovina and SEAVUS GROUP in Skopje Macedonia. He was named the best lecturer of WINDAYS 2008 while his lecture was also voted as the best. In addition, he was in TOP 10 lecturers at the MS SINERGY 2009 and MS VISIA 2009, 2010. Shares first place as the best lecturer of KulenDays 2009 and 2010 and PMI Conference 2009 in Zagreb. He is also a regular lecturer in the MS Community. He is a Certified Accountant and a PMP (Project Manager Professional) and a PMI-RMP (Risk Manager Professional), MCP, MCT, and Microsoft Certified Technical Specialist - Microsoft Project 2010. From 01.01.2012 awarded with MVP (Microsoft Most Valuable Proffesional - Microsoft Project)!
This entry was posted in MICROSOFT PROJECT, MS PROJECT 2019 and tagged , , . Bookmark the permalink.

Leave a comment