Hi,
today I will show you how can you put, and see Task progress using % Completeness in Microsoft Project for the Web!
As always I will first create a simple Project:

as you can see I have Tasks, Resources, and Dependencies. If I look at the Timeline View I will get:

Now let’s say that my Phase 1 is done, and I need to mark all Tasks as 100% completed:

and I will get:

As you can see, % complete for the Phase 1 is calculated as well (it is 10%). If I mark second and third Tasks as 100% completed, I will get:

Phase 1 is 99% completed, because even all Tasks are marked as 100% completed, it is not done, because Milestone is 1% (yes, it is 1% even it has 0 days duration). I will mark it as completed and I will get:

Now, let’s look at the Timeline View:

If I click on the Project name I will get:

Here I can see % Completeness for the whole Project (since it is not possible to see so called “Task 0” in Project for the Web).
Let’s say that Phase 2 is completed as well. I can go and mark each Tasks as 100% completed (and milestone, as well), or I can go to the Summary Task and mark it as 100% completed:

and I will get:

So the shortest way to mark Subtasks as 100% completed is to mark Summary Task as 100% completed.
Like this:
Like Loading...
Related
About Nenad Trajkovski
Location: Zagreb, Croatia
Occupation: Project Manager
Interests: Project Management and MS PROJECT
He was born in Zagreb, Croatia at 1963. After completing his college he started working on projects in different business areas (banking, manufacturing, automotive industry, distribution, oil companies, etc.) developing and implementing ERP systems into different companies. He has got a lot of experience working with people in different business processes and also possesses great knowledge in information technologies and financial services. Today he works as a business consultant, adn Project Manager in PERPETUUM MOBILE d.o.o. Zagreb. He is a regular lecturer for Project Management in MS Innovation Center in Varaždin, Logosoft Sarajevo in Bosnia and Herzegovina and SEAVUS GROUP in Skopje Macedonia. He was named the best lecturer of WINDAYS 2008 while his lecture was also voted as the best. In addition, he was in TOP 10 lecturers at the MS SINERGY 2009 and MS VISIA 2009, 2010. Shares first place as the best lecturer of KulenDays 2009 and 2010 and PMI Conference 2009 in Zagreb. He is also a regular lecturer in the MS Community. He is a Certified Accountant and a PMP (Project Manager Professional) and a PMI-RMP (Risk Manager Professional), MCP, MCT, and Microsoft Certified Technical Specialist - Microsoft Project 2010. From 01.01.2012 awarded with MVP (Microsoft Most Valuable Proffesional - Microsoft Project)!