Hi,
I will show you how you can easily adjust assignments and reschedule your tasks in the project.
First I will add four tasks to my project and they will be in manually scheduled mode, and I will not schedule them for the moment:
I will add 3 resources through the Resource sheet (John, Paul, and Mary):
I will now start the Team Planner View:
You can see that John Paul and Mary don’t have any tasks assigned, and that all tasks are unscheduled (because I left them in manually scheduled mode)
I will assign John to the Task 1 , Paul to the Task 2, and Mary to the Task 3. I will get:
You can see that those Tasks are assigned but not scheduled. Now I will drag and drop Task 1 and put it to start on Wednesday 11.05.2011:
and I will get:
You can see that the task is still in manual schedule mode, but it has estimated duration of 1 day.
I will now double click on Task 1 and put 3 day duration in the duration field:
and I will get:
Now John is assigned to the Task 1 and it is scheduled
I will drag and drop Task 2 from Paul to John and put it to start on Wednesday 11.05.2011 as well, and I will change its duration to 3 days (automatic scheduled). After that I will get:
You can see that John appears in a red color, and it means he is “over allocated”. Now I will simply drag and drop Task 2 from John to Paul and I will get:
You can see that John is not “over allocated” anymore.
Now I will double click on Task 4 and I will set 3 duration days (automatic scheduled):
and I will get:
You can see that Task 4 is now scheduled but not assigned.
So, generally you can play with Team Planner View to assign and reassign the Task however you want. You must remember that there are 4 areas in Team Planner View:
Finally, if you move a scheduled task (assigned or unassigned) to unscheduled area (assigned e.g. to someone) or unassigned you will actually delete actual work on that task. I will move Task 2 from assigned (to Paul) and scheduled (from 11.05.2011 to 13.05.2011) to unassigned and unscheduled area and I will get a warning:
And last, but not least, Tem Planner View is available only in MS PROJECT 2010 PROFESSIONAL VERSION!
In my next blog I will make the scenario more complicated because I will make a relationship between the tasks and THEN I will move them around!
See you,