How to hold Total Hours of work per Task when Actual Work is less then estimated hours in MS PROJECT 2016?

Hi,

Today I’m going to explain how to solve a problem which one of my Blog Readers have in MS PROJECT 2016.

Let us say that we have a Project with Task which is 6 weeks long. For this Task we have to hire external Consultant – Mary, and she will spend 8 hours per week, e.g. 48 hours in Total.

Firs I will create brand new Task with 6 weeks Duration and 48 hours of Work:

image

Notice, that Task is Fixed Duration type, because this is Demanded.

I will create one Resource – Mary the Consultant:

image

now I will assign Mary to the Task:

image

You can see that Mary is only 20% occupied on the Task, because she has to accomplish 48 hours in 6 weeks, which is 8 hours per week which is 8 hours / 5 days per week = 1,6 hours per day, and this is 20% of her capacity which is 8 hours per day.

OK, Let me switch to the Task Usage View, and on the Timescale I will show Months at the Middle Tier, and Weeks in the Bottom Tier, like this:

image

Now let’s say that Mary has worked 4 hours for first week. If I put it here like:

image

I will get:

image

But this is now what I wanted. I wanted to put 4 hours as Actual work (what I did), and that remaining work for this week is 0 hours (e.g. that Work, and Actual work are the same), and for all other weeks Work is the same (8 hours).

To make long story short, there is only one way to do it. For example, if Mary worked 4 hours at first and second week, and I want that remaining hours are 8 hours per week for the rest of those 4 weeks I should manually enter those numbers in the timescale:

image

So I put 4 hours at Work, and Actual Work. And you can see on the left part of the screen that Remaining work is 32 hours (8 hours per week per 4 weeks left).

So yes, it can be done but manually.

Regards!


Unknown's avatar

About Nenad Trajkovski

Location: Zagreb, Croatia Occupation: Project Manager Interests: Project Management and MS PROJECT He was born in Zagreb, Croatia at 1963. After completing his college he started working on projects in different business areas (banking, manufacturing, automotive industry, distribution, oil companies, etc.) developing and implementing ERP systems into different companies. He has got a lot of experience working with people in different business processes and also possesses great knowledge in information technologies and financial services. Today he works as a business consultant, adn Project Manager in PERPETUUM MOBILE d.o.o. Zagreb. He is a regular lecturer for Project Management in MS Innovation Center in Varaždin, Logosoft Sarajevo in Bosnia and Herzegovina and SEAVUS GROUP in Skopje Macedonia. He was named the best lecturer of WINDAYS 2008 while his lecture was also voted as the best. In addition, he was in TOP 10 lecturers at the MS SINERGY 2009 and MS VISIA 2009, 2010. Shares first place as the best lecturer of KulenDays 2009 and 2010 and PMI Conference 2009 in Zagreb. He is also a regular lecturer in the MS Community. He is a Certified Accountant and a PMP (Project Manager Professional) and a PMI-RMP (Risk Manager Professional), MCP, MCT, and Microsoft Certified Technical Specialist - Microsoft Project 2010. From 01.01.2012 awarded with MVP (Microsoft Most Valuable Proffesional - Microsoft Project)!
This entry was posted in MICROSOFT PROJECT, MS PROJECT 2016 and tagged , , . Bookmark the permalink.

Leave a comment