Customized resource calendar and its effect on task duration in MS PROJECT 2016!

Hi,

my blog reader has a question and I’m going to repro his scenario step by step, and answer the question using MS PROJECT 2016.

First I will create a 5 day Task:

image

There are 2 resources assigned to the project –  John and Mary:

SNAGHTML7c215204

Mary is supposed to work on a week  to 4-day 10hrs/week  schedule, so I customize her personal calendar:

image

and:

image

So Mary is supposed to work 10 hours per day from Monday to Thursday, but she is off at Friday. Now I will assign Mary to the Task:

image

As you can see, Duration is 5 days, even Mary is not working at Friday. How is it so?

Let see here:

image

and:

SNAGHTML7c29a6b5

and then:

image

As you can see 1 day of Duration is 8 hours! (see hours per Day option in the picture above).

So for Mary, Total work is 40 hours (10 at Monday, 10 at Tuesday, 10 at Wednesday, and 10 at Thursday). Duration of the Task is 40 hours (Total) / 8 hours per day = 5 days.

Now I will  add John to the Task, and he is “regular” worker, so he is suppose to work 8 hours per day from Monday to Friday:

image

The question from my Blog reader is: “How Project calculates the new 6-day Duration for the task?”

And the Answer is easy. When only Mary was assigned to the Task the Task duration wad 5 days. Now John will work 1 day more. As simple as that. He will work at Friday. So those 5 days + 1 days (Friday) is 6 days duration. Or let me explain that day by day:

  • Monday to Thursday: John works 8 hours = 1 day. Mary works 10 hours = 10to be worked /8 (hours per day) = 1,25 days. Duration is longest one, so it is 1,25 days
  • Friday: John works 8 hours = 1 day. Mary does not work. Duration is, obviously 1 day.
  • Total: 1,25 (Monday) + 1,25 (Tuesday) + 1,25 (Wednesday) + + 1,25 (Thursday) + 1 (Friday) = 6 days

Hope this helps.

Regards!

Unknown's avatar

About Nenad Trajkovski

Location: Zagreb, Croatia Occupation: Project Manager Interests: Project Management and MS PROJECT He was born in Zagreb, Croatia at 1963. After completing his college he started working on projects in different business areas (banking, manufacturing, automotive industry, distribution, oil companies, etc.) developing and implementing ERP systems into different companies. He has got a lot of experience working with people in different business processes and also possesses great knowledge in information technologies and financial services. Today he works as a business consultant, adn Project Manager in PERPETUUM MOBILE d.o.o. Zagreb. He is a regular lecturer for Project Management in MS Innovation Center in Varaždin, Logosoft Sarajevo in Bosnia and Herzegovina and SEAVUS GROUP in Skopje Macedonia. He was named the best lecturer of WINDAYS 2008 while his lecture was also voted as the best. In addition, he was in TOP 10 lecturers at the MS SINERGY 2009 and MS VISIA 2009, 2010. Shares first place as the best lecturer of KulenDays 2009 and 2010 and PMI Conference 2009 in Zagreb. He is also a regular lecturer in the MS Community. He is a Certified Accountant and a PMP (Project Manager Professional) and a PMI-RMP (Risk Manager Professional), MCP, MCT, and Microsoft Certified Technical Specialist - Microsoft Project 2010. From 01.01.2012 awarded with MVP (Microsoft Most Valuable Proffesional - Microsoft Project)!
This entry was posted in Micsrosoft Project 2016, MS PROJECT 2016, PMI, PRoject Management and tagged , . Bookmark the permalink.

Leave a comment