Setting up MS PROJECT 2010 for my Project and Creating the Project Plan

 

Hi,

Before planning, I will set up MS PROJECT 2010 for my Project.

First I will open a brand-new Project.

image

After that I will put some Basic information about my Project here:

image 

and then:

image

 

Now I will put some additional information for my Project here:

image

As you can see I choose to Schedule from: Project Start Date. Why? Well, because If I choose Schedule from: Project Finish Date, all of my task will be scheduled with Start As Late AS Possible constraint, and I don’t want that. And, John and Mary (my Sponsors) don’t have a specific date for their wedding.

Do you want an example of Project when you have to establish Schedule from: Project Finish Date? PREPARING THE OLIMPIC GAMES, or THE WORLD FOOTBALL CHAMPIONSHIP! Why? Because when you have such kind of event, you and the rest of the world know EXACTLY when this event will start. So this Start date of the event is your Finish Date of the Project!

Now I will setup default working time. If you want a know about scheduling problems in MS PROJECT 2010, and how to manage working time and calendars without getting in trouble read my post: https://ntrajkovski.wordpress.com/2011/04/12/scheduling-problems-in-ms-project-2010-2/

In the File Tab click on the Options  button and you will get:

image

I decide that regular working time will be from 08:00 to 17:00 with 8 hours per day, and that means that I will have 1 hour for lunch break. My week will have 40 working hours, and my month will have 20 working days.

I decided that every new task created will be in Manually Scheduled mode (an that is a brand-new feature in MS PROJECT 2010, and when I add new task in Auto scheduled mode it will have default Start Date same as the Project Start Date (which is 01.08.2011). The another option is Current Date.

You will se in my future posts how this working time is in correlation with Project, Task and Resource Calendars.

Why did I decide to have every new task in Manually Scheduled mode? Because I have no idea about task duration (for now!), when will it start or finish, and I do not want default duration of 1 day (which is in Auto scheduled mode). And, finally I want to write in Duration, Start Date and End Date field whatever I want (for now!)

Now, I will set US dollar as currency. In the File Tab click on the Options button and you will get:

image

and I will get:

image

Before saving my Project I want to see Project Summary Task:

image

Finally, I will save my Project:

image

and then:

image

That’s all for initial set up!

 

Best Regards!

Unknown's avatar

About Nenad Trajkovski

Location: Zagreb, Croatia Occupation: Project Manager Interests: Project Management and MS PROJECT He was born in Zagreb, Croatia at 1963. After completing his college he started working on projects in different business areas (banking, manufacturing, automotive industry, distribution, oil companies, etc.) developing and implementing ERP systems into different companies. He has got a lot of experience working with people in different business processes and also possesses great knowledge in information technologies and financial services. Today he works as a business consultant, adn Project Manager in PERPETUUM MOBILE d.o.o. Zagreb. He is a regular lecturer for Project Management in MS Innovation Center in Varaždin, Logosoft Sarajevo in Bosnia and Herzegovina and SEAVUS GROUP in Skopje Macedonia. He was named the best lecturer of WINDAYS 2008 while his lecture was also voted as the best. In addition, he was in TOP 10 lecturers at the MS SINERGY 2009 and MS VISIA 2009, 2010. Shares first place as the best lecturer of KulenDays 2009 and 2010 and PMI Conference 2009 in Zagreb. He is also a regular lecturer in the MS Community. He is a Certified Accountant and a PMP (Project Manager Professional) and a PMI-RMP (Risk Manager Professional), MCP, MCT, and Microsoft Certified Technical Specialist - Microsoft Project 2010. From 01.01.2012 awarded with MVP (Microsoft Most Valuable Proffesional - Microsoft Project)!
This entry was posted in MICROSOFT PROJECT, Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management and tagged , , , . Bookmark the permalink.

7 Responses to Setting up MS PROJECT 2010 for my Project and Creating the Project Plan

  1. Char B's avatar Char B says:

    Thank you, very helpful

  2. Best's avatar Best says:

    This is quite elaborate and helpful. Thanks a mil.

  3. Juan Cisneros's avatar Juan Cisneros says:

    Thanks, is there a way to change the default calendar so that every new project is created with the predefined working time?

    • Nenad Trajkovski's avatar Nenad Trajkovski says:

      Yes. You can make your own Calendar (recommended), or mmodify existing one (not recommended), and make a Template!

  4. Yella Reddy's avatar Yella Reddy says:

    Thanks Helped me…

  5. Zach's avatar Zach says:

    An intriguing discussion is definitely worth comment. I believe that you need to publish more about this subject matter, it might not be a taboo matter but usually folks don’t discuss such issues. To the next! Many thanks!!

Leave a reply to Best Cancel reply