Hi!
Here is Scenario!
I want to Manage my Project in MS PROJECT PRO 2013! I want to upload an mpp file in SharePoint 2013, and there I want to have all my Project Documents, and I want to track Project Issues!
I have my Site in SharePoint Server 2013:
I’ will create one simple Project with three Tasks and Three Resources in MS PROJECT PRO 2013:
and:
After assigning this Resources to Tasks I will have:
I’ll save this file in My Desktop and I will upload it on the SharePoint:

and:
and Finally:
Now I have:
If I click on My Project link it will be opened in MS PROJECT!
I will add Project plan as well:
and I have it here:
Finally I want to add some Issues for My Project. Remember that issue is not the same thing as a Risk! Risk is something that has probability greater that 0%, and less than 100%! Issue is, on the other hand, something that is 100% fact!
and:
As you can see, because I’, using Local Resources for My Project, I can’t assign this issue to them!
This is the simplest way of using SharePoint as Repository for your Project files, documents and issues!
Regards!
About Nenad Trajkovski
Location: Zagreb, Croatia
Occupation: Project Manager
Interests: Project Management and MS PROJECT
He was born in Zagreb, Croatia at 1963. After completing his college he started working on projects in different business areas (banking, manufacturing, automotive industry, distribution, oil companies, etc.) developing and implementing ERP systems into different companies. He has got a lot of experience working with people in different business processes and also possesses great knowledge in information technologies and financial services. Today he works as a business consultant, adn Project Manager in PERPETUUM MOBILE d.o.o. Zagreb. He is a regular lecturer for Project Management in MS Innovation Center in Varaždin, Logosoft Sarajevo in Bosnia and Herzegovina and SEAVUS GROUP in Skopje Macedonia. He was named the best lecturer of WINDAYS 2008 while his lecture was also voted as the best. In addition, he was in TOP 10 lecturers at the MS SINERGY 2009 and MS VISIA 2009, 2010. Shares first place as the best lecturer of KulenDays 2009 and 2010 and PMI Conference 2009 in Zagreb. He is also a regular lecturer in the MS Community. He is a Certified Accountant and a PMP (Project Manager Professional) and a PMI-RMP (Risk Manager Professional), MCP, MCT, and Microsoft Certified Technical Specialist - Microsoft Project 2010. From 01.01.2012 awarded with MVP (Microsoft Most Valuable Proffesional - Microsoft Project)!