Extended duration when Successor has been started in MS PROJECT 2016

Hi,

my Blog reader has a problem:

“So what if we aren’t moving the project, just adding time to a task where a dependent task was able to start early. As an example
Task A 10 days
Task B 2 days
Task C 5 days

A is a predecessor of B. B is a predecessor of C.
Work is started on B, 50% complete
It is determined that A is going to take longer, 15 days

The Problem: Changing A to 15 days doesn’t cause the times to recalculate for B and C because of the work percentage for B being 50%. Is there an elegant way around this?

The only way I’ve been able to do this is to delete out the percentage, add the days to A, then re-enter the percentages. That isn’t hard on such a small example. But in real life, with larger projects, it just doesn’t work. Suggestions?”

Well, this need an brief explanation, and I will do it in MS PROJECT 2016!

First I’m create Project with schedule as was described by my blog Reader:

image

As you can see, this is Finish to Start relation. Now, let’s say that Task B is 50% completed, as planned:

image

and I will get:

image

Now, let’s suppose that Task A will have 15 days Duration instead of 10:

image

As you can see, Finish date of the Project is moved to Thursday 26.11.2015. BUT! 50% of previous finished Task 2 is not moved. And that make sense, because MS PROJECT is not supposed to move finished Tasks, or piece od partially Finished Tasks anywhere! If something is done, it is done! No matter of other Tasks! And as you can see the remaining part of Task B is rescheduled to the first working day after Task A is supposed to be finished. For example, if Task A has 12 days duration, the remaining part of Task B will start at Wednesday, 18.11.2015.

image

The question which really matters here is: “Do we have a right schedule for this Project?” Why is this question so important? As you can see, Task A is Predecessor of Task B, with Finish-to-Start Relationship. And, Task B has been started before Task A has been 100% finished. Something is wrong with that. So if this is case, and Task B should be started before Task A is 100% finished we should consider different relationship (Start-to-Start, for example).

Hope this helps!

Regards.

Advertisement

About Nenad Trajkovski

Location: Zagreb, Croatia Occupation: Project Manager Interests: Project Management and MS PROJECT He was born in Zagreb, Croatia at 1963. After completing his college he started working on projects in different business areas (banking, manufacturing, automotive industry, distribution, oil companies, etc.) developing and implementing ERP systems into different companies. He has got a lot of experience working with people in different business processes and also possesses great knowledge in information technologies and financial services. Today he works as a business consultant, adn Project Manager in PERPETUUM MOBILE d.o.o. Zagreb. He is a regular lecturer for Project Management in MS Innovation Center in Varaždin, Logosoft Sarajevo in Bosnia and Herzegovina and SEAVUS GROUP in Skopje Macedonia. He was named the best lecturer of WINDAYS 2008 while his lecture was also voted as the best. In addition, he was in TOP 10 lecturers at the MS SINERGY 2009 and MS VISIA 2009, 2010. Shares first place as the best lecturer of KulenDays 2009 and 2010 and PMI Conference 2009 in Zagreb. He is also a regular lecturer in the MS Community. He is a Certified Accountant and a PMP (Project Manager Professional) and a PMI-RMP (Risk Manager Professional), MCP, MCT, and Microsoft Certified Technical Specialist - Microsoft Project 2010. From 01.01.2012 awarded with MVP (Microsoft Most Valuable Proffesional - Microsoft Project)!
This entry was posted in MICROSOFT PROJECT, Microsoft Project 2013, Micsrosoft Project 2016, PMI, PRoject Management and tagged . Bookmark the permalink.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s