Tag Archives: MICROSOFT PROJECT 2016. MICROSOFT PROJECT 2016 – Schedule
Task Duration and Resource additional day off in MS PROJECT 2016
Hi, today I will show you what happens if you assign resource to the Task, and afterwards put, for example, day off for that Resource in MS PROJECT 2016 First, I’m going to create simple Project: I will now create … Continue reading
Extended duration when Successor has been started in MS PROJECT 2016
Hi, my Blog reader has a problem: “So what if we aren’t moving the project, just adding time to a task where a dependent task was able to start early. As an exampleTask A 10 daysTask B 2 daysTask C … Continue reading