Location: Zagreb, Croatia Occupation: Project Manager Interests: Project Management and MS PROJECT He was born in Zagreb, Croatia at 1963. After completing his college he started working on projects in different business areas (banking, manufacturing, automotive industry, distribution, oil companies, etc.) developing and implementing ERP systems into different companies. He has got a lot of experience working with people in different business processes and also possesses great knowledge in information technologies and financial services. Today he works as a business consultant, adn Project Manager in PERPETUUM MOBILE d.o.o. Zagreb. He is a regular lecturer for Project Management in MS Innovation Center in Varaždin, Logosoft Sarajevo in Bosnia and Herzegovina and SEAVUS GROUP in Skopje Macedonia. He was named the best lecturer of WINDAYS 2008 while his lecture was also voted as the best. In addition, he was in TOP 10 lecturers at the MS SINERGY 2009 and MS VISIA 2009, 2010. Shares first place as the best lecturer of KulenDays 2009 and 2010 and PMI Conference 2009 in Zagreb. He is also a regular lecturer in the MS Community. He is a Certified Accountant and a PMP (Project Manager Professional) and a PMI-RMP (Risk Manager Professional), MCP, MCT, and Microsoft Certified Technical Specialist - Microsoft Project 2010. From 01.01.2012 awarded with MVP (Microsoft Most Valuable Proffesional - Microsoft Project)!

How to Change View in MS PROJECT 2019?

Hello, Today I will show you how to change View in MS PROJECT 2019! Let’s say that we have Project like this: As you can see, for this Project I have resources: and if I apply Cost Table on the … Continue reading

Posted in MICROSOFT PROJECT, MICROSOFT PROJECT 2019 | Tagged | Leave a comment

Calendar View in Master Project–Microsoft Project 2019

Hi, today I will show you how to see Tasks in Calendar View within Master Project, using MS PROJECT 2019. I have Two Projects: and Second: Both Projects are using same Resource pool: and I created Master Project: Now I … Continue reading

Posted in MICROSOFT PROJECT 2019 | Tagged | Leave a comment

How to make every second Saturday as working day in MS PROJECT 2019

Hi, sometimes, in your Project you will need to make some Saturdays (or Sundays) make as a working day. Let’s say that I need to work every second Saturday. I have a simple Project: I want to make every second … Continue reading

Posted in MICROSOFT PROJECT 2019, MS PROJECT 2019 | Tagged | Leave a comment

Specific Resource overallocation during the day using MS PROJECT 2019

Hi, I have a question from my Blog reader: “I want to solve overallocation of R1, since it is assigned to Task1 and Task2. I want to divide the work of R1 between  Task 1 and Task 2 to solve … Continue reading

Posted in MS PROJECT 2019 | Tagged | Leave a comment

Estimation in hours and Resource Assignments with Fixed work Tasks in MS Project 2019

Hi, very often Tasks are estimated by effort, not duration. And Tasks are fixed work type. Now the question is: “How many hours will each resource spend at the Task?” I will show that in MS PROJECT 2019.¸ Let’s say … Continue reading

Posted in MS PROJECT 2019 | Tagged | Leave a comment

Actual duration and Actual start “problem” in MS PROJECT 2019

Hi, I have a question from blog reader: “Hi Nenad, I would like to track the progress in the following scenario:Task A: 3,5 d durationTask B: 3 d duration with a constraint FS with task AProgress: Say that Task A … Continue reading

Posted in MICROSOFT PROJECT 2019 | Tagged , | Leave a comment

How to apply same filter on different tables in MS PROJECT 2019

Hi, today I will show you how to apply same filter only once, and use different tables in MS PROJECT 2019. First, I’m going to create a simple Project: and I will create Resources needed for the Project: Finally I … Continue reading

Posted in MICROSOFT PROJECT 2019 | Tagged , | Leave a comment