Category Archives: Project for the Web
Task Start and Finish time in Microsoft Project for the Web
Hi, Today I will show you in a short Post how to see at what Time should Task start and when it should ended. To do that I will create a very simple Project: or (Timeline View): Start and Finish … Continue reading
How to find right Project in Microsoft Project for the Web?
Hi, today I will show you how to find right Project, if you have many of them, using Microsoft Project for the Web! When I log myself to the Project for the Web I will get next Screen: In a … Continue reading
Task progress with % completeness in Microsoft Project for the Web
Hi, today I will show you how can you put, and see Task progress using % Completeness in Microsoft Project for the Web! As always I will first create a simple Project: as you can see I have Tasks, Resources, … Continue reading
How to use Office 365 Groups with Microsoft Project for the Web
Hello, Today I will show you how to use Groups with Microsoft Project for the Web. First I will create brand new Simple Project: The Group is needed when I am going to assign First Resource to my Task. Let’s … Continue reading
Task Filters in Microsoft Project for the Web
Hello, today I will show you how can you filter Tasks in the Microsoft Project for the Web, and on what can you apply filter. As always, I will first create new Project: If I look at the Timeline View, … Continue reading
Color indicators for Finish date in Microsoft Project for the Web
Hi, Today I will show you color indicators for Finish date in Microsoft Project for the Web! First I will create simple Project with five Tasks: Current date is 05/10/2020, as you can see in Timeline View: In a Grid … Continue reading
Driving Tasks in Microsoft Project for the Web
Hi, Today, I will show you how can you see driving Tasks in Microsoft Project for the Web. First I will crate new Project: As you can see, Task 3 has two Predecessors: Task 1, and Task 2. If I … Continue reading
Task constraints in Microsoft Project for the Web
Hi, as you already know, in Microsoft Project online or desktop version there are lot Task constraints (for example: Start No Earlier Than, Finish No Earlier Than, Must Start On, Must Finish On, etc.) In Microsoft Project for the Web … Continue reading
How to setup nonworking days for Resource in Project for the Web?
Hit, Today I will show you how to setup nonworking days in Project For the Web. Firs of all, I will assume that my Particular Resource has setup working time. I will open Dynamics 365: and then: I will choose … Continue reading
How to customize Working Time for particular Resource in Microsoft Project for the Web?
Hi, today I sill show you hot to customize Calendar and working time for Particular Resource in Microsoft Project for the Web. First of all, create your own Calendar Template, according to your Time Zone! Let’s say that my Calendar … Continue reading