Setting Up Resources in MS PROJECT 2010! Budget Resource, and Detailed Resource information!

 

Hi,

If you have a Budget for your project you can work with it in MS PROJECT 2010. Frankly, the solution with the Budget in MS PROJECT 2010 is not something what make me happy. I think that it could, and should be much better than it is now. But, until next version of MS PROJECT, I will explain how can you work with those resources.

First of all, when you have a Budget Resource, make sure that you put the different name convention to that resource (use UPER CASE, or prefix like B-). Let say that we have four budgeted Resources for our Project:

image

As you can see, two of them are Work type Resources, one is Material type, and one is Cost type. I also put for Work and Material resources Standard rate! But, I know what would you ask! How MS PROJECT 2010 knows that those Resources are Budget type? Obviously not by the B- prefix. Well IT DOES NOT KNOW until you tell it that those are Budget type. Double click on each of Resource for which you want to become a Budget and check:

image

After you check all your Budget Resources you will get:

image

 

As you can see, Max units, and Standard rate are empty now! Why? Because you do not need them. You will assign cost for those budgeted resources to the resources through Task and/or Resource usage Views. When we get to the point where I will Set up a Budget I will show you how can you do it! For now Remember that you can’t assign Budgeted Resources to anything else then PROJECT SUMMARY TASK. That means that if you have budget for one, particular, Task you can not assign that budget to that task, but rather to a project as a whole, and that is something I am not happy about. I will write about this when I come to the Assigning Resources to the Tasks!

If you want to add some additional information for your Resource (like windows account, Email, note, or hyperlink, you can do it very easy.

You can double click on your Resource name, or you can go to the Resource information through Resource Tab:

image

and You will get:

image

I put my email address, and Windows Account. That was in General TAB. If I want put some note about Resource I can do it through Notes Tab:

image

If you want to add a hyperlink to the Resource you can do it like this:

image

After that you can enter the Hyperlink:

image

After that you will see Indicator right from the Resource:

image

Rest your mouse pointer at the Indicator field and you will see:

image

If you want to open the hyperlink, right click to the Indicator field and then follow this:

image

 

Dear fellows that was all of the easy part of Resource. From my next post I will start with Assigning Resources to the Tasks! It will take me some time and posts but those are almost the most significant things to remember If you want to understand the logic of MS PROJECT 2010.

Until then,

All the Best!

Unknown's avatar

About Nenad Trajkovski

Location: Zagreb, Croatia Occupation: Project Manager Interests: Project Management and MS PROJECT He was born in Zagreb, Croatia at 1963. After completing his college he started working on projects in different business areas (banking, manufacturing, automotive industry, distribution, oil companies, etc.) developing and implementing ERP systems into different companies. He has got a lot of experience working with people in different business processes and also possesses great knowledge in information technologies and financial services. Today he works as a business consultant, adn Project Manager in PERPETUUM MOBILE d.o.o. Zagreb. He is a regular lecturer for Project Management in MS Innovation Center in Varaždin, Logosoft Sarajevo in Bosnia and Herzegovina and SEAVUS GROUP in Skopje Macedonia. He was named the best lecturer of WINDAYS 2008 while his lecture was also voted as the best. In addition, he was in TOP 10 lecturers at the MS SINERGY 2009 and MS VISIA 2009, 2010. Shares first place as the best lecturer of KulenDays 2009 and 2010 and PMI Conference 2009 in Zagreb. He is also a regular lecturer in the MS Community. He is a Certified Accountant and a PMP (Project Manager Professional) and a PMI-RMP (Risk Manager Professional), MCP, MCT, and Microsoft Certified Technical Specialist - Microsoft Project 2010. From 01.01.2012 awarded with MVP (Microsoft Most Valuable Proffesional - Microsoft Project)!
This entry was posted in MICROSOFT PROJECT, Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management and tagged , , , . Bookmark the permalink.

11 Responses to Setting Up Resources in MS PROJECT 2010! Budget Resource, and Detailed Resource information!

  1. galadar's avatar galadar says:

    Hi Dears
    thank you Mr. Nenad, I appreciate your works, I like to say I found this article it’s link posted below, it may be helpful to our friends.

    http://www.msprojectnow.com/Knowledge/Blog/tabid/142/entryid/440/Assigning-Budget-Resources-in-Microsoft-Project-2010.aspx

    thank you
    with respect …

    • galadar's avatar galadar says:

      also you may found this useful, that is the definition of this kind of costs that has been defined by Microsoft itself:

      Budget Resource: A budget resource captures the maximum capacity for a project to consume money, work, or material units for a project. Budgets can only be applied at the project level by assigning a budget resource to the project summary task.

      with regards …

  2. Miky's avatar Miky says:

    I am not sure how useful the budget resource feature is. In my mind the budget is set with the baseline. I know that I am missing something but can’t figure out what. What is difference here, and how does it affect Earned Value calculations? Please help.

    • Nenad Trajkovski's avatar Nenad Trajkovski says:

      Budgeted Resources are, from my point of view, useless. And those are not consiedered while calculating EVM!

      • Srđan Điđo Drljača's avatar Srđan Điđo Drljača says:

        What is maximum number of budget resources per project?
        Sorry Nenad 😦 but I have to disagree. We found them very useful when calculating income on the project.

      • Nenad Trajkovski's avatar Nenad Trajkovski says:

        You can use them for income, of xourse. But for other things there are more or less poor!

  3. alimi shakirat's avatar alimi shakirat says:

    and secondly, give detail imformation on design and d principle to the plannig and developmeng of audio visual resources

  4. Refugio Schomacker's avatar Refugio Schomacker says:

    It’s perfect time to make some plans for the future and it’s time to be happy. I’ve read this post and if I could I want to suggest you few interesting things or advice. Perhaps you can write next articles referring to this article. I wish to read even more things about it!

  5. Shirleen Denni's avatar Shirleen Denni says:

    Great beat ! I wish to apprentice while you amend your site, how could i subscribe for a blog site? The account helped me a acceptable deal. I had been tiny bit acquainted of this your broadcast offered bright clear concept

  6. Candi Carros's avatar Candi Carros says:

    Great blog here! Also your website loads up very fast! What host are you using? Can I get your affiliate link to your host? I wish my website loaded up as fast as yours lol

Leave a reply to Shirleen Denni Cancel reply