Hi,
as you remember in my last post created two new custom fields: Budget for Task, and Variance from Actual. To use this two fields I have to put them in some table. The best approach for my example is to put them into the Cost table:
and then:
and I will get the screen with all fields in the Cost Table. I will put the cursor in the first blank row and I will pick up those two new custom fields:
and I will fill the other field attributes, as shown in the picture below:
and I will get:
Now I will fill the Task budget field for each Task:
OK. I will assign Resource 1 to the Task 1, Resource 2 to the Task 2, etc! After that I will get:
- Task 1 has 1 day duration, e.g. 8 hours, and Resource 1 has $100/hour and it means 8 * 100 = $800
- Task 2 has 2 days duration, e.g. 16hours, and Resource 2 has $200/hour and it means 16 * 200 = $3.200
- Task 3 has 3 days duration, e.g. 24 hours, and Resource 3 has $300/hour and it means 24 * 300 = $7.200
- Task 4 has 2 days duration, e.g. 16 hours, and Resource 4 has $400/hour and it means 16 * 400 = $6.400
- Total cost for the project is = $800 + $3.200 + $7.200 + $6.400 = $17.600
Now, suppose that work is done for all tasks. Task 1 is 100% completed, and it is on time:
Because budget for the Task 1 is $1000, and Actual cost is $800, Budget – Actual = $1.000 – $800 = $200
Now I will full the Actuals for the Task 2:
and then:
Task 2 has 3 days duration instead of 2. I will get:
Actual cost for the Task 2 is: 3 days (3*8=24) hours * $200/hour for Resource 2= $4.800. Budget is $3.000, and the Budget – Actual is $3.000 – $4.800 = –$4.800.
Now I will say that Task 3 was finished 2 days earlier:
and I will get:
Actual cost for the Task 3 is: 1 day1 (1*8=8) hours * $300/hour for Resource 3= $2.400. Budget is $8.000, and the Budget – Actual is $8.000 – $2.400 = $5.600.
Finally, I will say that Task 4 was finished 5 days latter than planned:
and I will get:
Actual cost for the Task 4 is: 7 days (7*8=56) hours * $400/hour for Resource 4= $22.400. Budget is $4.000, and the Budget – Actual is $4.000 – $22.400 = –$18.400.
And in the Summary Task you can see the total value for the Project budget, and Project Actual cost, and the Budget – Actual = –$14.400
It wasn’t so complicated, was it?
Regards!
This topic is really useful.
u shut him up, huh?
Thansks for you post. But you are unnecessarily complicating it by introducing custom columns. Go to cost table, MPP would show you, fixed cost, total cost (fix cost+variable resource cost, based on the mentioned billing rates), Baseline cost, Actual Cost, Cost Variance as you keep on tracking the project at any point in time.
I know that. But what if you want to put Budgeted Costs for each Task which are different than calculated by MS PROJECT? That was my point!