How to get percentage of costs in MS PROJECT 2010 or 2013!

  Hi, my Blog reader have a problem! He want to know how much money did he spend and, he wants that in percentage of Baseline in MS PROJECT 2010. He had sent me his mpp file! Here it is: … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, PRoject Management | Tagged , , , | 4 Comments

CREATING OWN BUDGET IN MS PROJECT 2010–PART 2

Hi,   as you remember in my last post created two new custom fields: Budget for Task, and Variance from Actual.  To use this two fields I have to put them in some table. The best approach for my example … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , , , | 4 Comments

CREATING OWN BUDGET IN MS PROJECT 2010–PART 1

  Hi, I will explain how to make and track your own Budget in MS PROJECT 2010! Suppose that you want to have a budget (in money) for each task, and that you want to track variance from the actual … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , , , | 4 Comments

Setting Up the Project Budget

Hi, I will try to explain how to put the Budget in your Project with MS PROJECT 2010. I will repeat part of my Post from 13.10.2011! First of all, when you have a Budget Resource, make sure that you … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , , , | 4 Comments