Effort and non effort driven Tasks in MS PROJECT 2013

 

Hi,

here is the question from my Blog reader:

“Nenad:
Thanks very much for the posting!
Do you know if there is any way of setting up a different default for this operation? More specifically, suppose that I have many tasks assigned to “John” and I want to reduce the project time by hiring another person (it could be “Mary”) to share the work with John. If I simply add Mary to all tasks, MSP would assume that all I want to increase the amount of work all those tasks need – which is not the reason I’m adding Mary.
Would I have to add Mary one task after another, changing each one individually to “Reduce duration so the task end sooner, but requires same amount of work (person-hours)”? Or is that a way of adding Mary to all tasks with the “Reduce duration…” option?”

I wrote about that in one of my previous posts, but I will explain this issue again with MS PROJECT 2013.

First of all, where is the difference between Effort Driven, and Non Effort Driven Tasks in MS PROJECT 2013?

Effort driven Tasks are those which will (if you do not change it manually), reduce duration if you assign additional Resource to the Task. For example, if you have PAINT THE WALL Task, and it has duration = 4 days, and you have only one Resource assign to that task, when you add new Resource to that Task, duration will be 2 days!

On the other hand, Non effort driven Tasks are those which will not (if you do not change it manually), reduce duration if you assign additional Resource to the Task, but it will increase total amount of work (hours). For example, if you have READ THE BOOK Task, and it has duration = 4 days, and you have only one Resource assign to that task, when you add new Resource to that Task, duration will still be 4 days, but the total amount of work for that Task will be 4 days * 2 Resources * 8 hours/day = 64 hours.

Let me show you that. I have those two Tasks here:

image

and I have two Resources:

image

I will Assign John to the Paint the wall Task, and Mary to the Read the Book  Task, and I will get:

image

Let’s see where can we find if the Task is or is not effort driven:

image

Now I have Paint the wall as effort driven Task, and Read the Book, as Non effort driven Task.

Now I am going to assign Mary to the Paint the wall Task:

image

and I will get:

image

Now let’s see Read the Book Task:

image

You can see that the Task in Non effort driven, and that Mary will spend 32 hours of work (4 days * 8 hours per day).

I will add John to that Task:

image

and I will get:

image

You can see that Duration is same, and John will spend additional 32 hours on that Task, so it takes total of 64 hours for that Task.

But what if you always want shorter Task duration, after assigning additional resource, so you do not have to make each Task effort driven manually. You can do it here: File->Options, and than:

image

That’s it! Regards!

Unknown's avatar

About Nenad Trajkovski

Location: Zagreb, Croatia Occupation: Project Manager Interests: Project Management and MS PROJECT He was born in Zagreb, Croatia at 1963. After completing his college he started working on projects in different business areas (banking, manufacturing, automotive industry, distribution, oil companies, etc.) developing and implementing ERP systems into different companies. He has got a lot of experience working with people in different business processes and also possesses great knowledge in information technologies and financial services. Today he works as a business consultant, adn Project Manager in PERPETUUM MOBILE d.o.o. Zagreb. He is a regular lecturer for Project Management in MS Innovation Center in Varaždin, Logosoft Sarajevo in Bosnia and Herzegovina and SEAVUS GROUP in Skopje Macedonia. He was named the best lecturer of WINDAYS 2008 while his lecture was also voted as the best. In addition, he was in TOP 10 lecturers at the MS SINERGY 2009 and MS VISIA 2009, 2010. Shares first place as the best lecturer of KulenDays 2009 and 2010 and PMI Conference 2009 in Zagreb. He is also a regular lecturer in the MS Community. He is a Certified Accountant and a PMP (Project Manager Professional) and a PMI-RMP (Risk Manager Professional), MCP, MCT, and Microsoft Certified Technical Specialist - Microsoft Project 2010. From 01.01.2012 awarded with MVP (Microsoft Most Valuable Proffesional - Microsoft Project)!
This entry was posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, PMI, PRoject Management and tagged , , , . Bookmark the permalink.

4 Responses to Effort and non effort driven Tasks in MS PROJECT 2013

  1. il0veass's avatar il0veass says:

    Thanks so much for this explanation! I spent way more time than I’d like to admit just trying to make the duration go down when i add someone so thanks!!

  2. Vishal's avatar Vishal says:

    Thanks a lot.. Very well explained.

  3. michael jijingi's avatar michael jijingi says:

    Thanks for the insight . it appears to me is easier using Ms project to compute Task durations and constraints . can you kindly give me references to where to source for Ms projects program to assist me in computing task and constraints in my subsequent school works. Michael.

    Date: Mon, 6 May 2013 08:13:54 +0000 To: michael.jijingi@hotmail.com

    • Nenad Trajkovski's avatar Nenad Trajkovski says:

      I do not understand what do you need. Can you give me a little bit more information, so I will help you?

Leave a comment