Hi,
Today I’ll show another way of adding Resource after it is, for example, 40% Finished.
first, I’ll show you pictures from my Previous Post, so I will create on simple Project in MS PROJECT 2013:
and I will create tow Resources like this:
and I’ll assign John to the Task:
Now I will make Task 40% Completed, like this:
and:
Now I’ll use Detail View with Task form:
As you can see, Task is 40% Finished. I’ll now add Mary as Resource form the Gant Chart:
and I’ll get:
In this case, I will get EXACT what I’ve got in my Previous Post, e.g.:
As you can see, Mary will work only 24 hours (not 40) for this Task! Let’s see Task Usage View:
As you can see, John is done with work on Monday and Tuesday (this is 40% of Job done), and now wee need Mary. Mary will work 8 house at Wednesday, Thursday, and Friday. Duration remains the same e.g. 5 days.
If I choose this Option:
I will get:
So duration is shortened, and Total hours (40) are same. Let’s look at Task Usage View:
As you can see, John is done with work on Monday and Tuesday (this is 40% of Job done), and now wee need Mary. John and Mary will split the Remaining work (32 hours) at Wednesday (John will work 8 hours, and Mary as well), and Thursday (John will work 4 hours, and Mary as well). So, work distribution will be:
Monday –> John 8 hours TOTAL: 8 hours
Tuesday –> John 8 Hours TOTAL: 8 hours
Wednesday-> John 8 Hours, Mary 8 Hours TOTAL: 16 hours
Thursday –> John 4 hours, Mary 4 Hours TOTAL: 8 hours
GRAND TOTAL: 40 hours
Finally I’ll choose the Third Option:
and I’ll get:
Again, I’m going to use Task Usage View with Peak field:
Duration remains same, But for the Rest work, John and Mary will work less hours per day. So, work distribution will be:
Monday –> John 8 hours TOTAL: 8 hours
Tuesday –> John 8 Hours TOTAL: 8 hours
Wednesday-> John 4 Hours, Mary 4 Hours TOTAL: 8 hours
Thursday –> John 4 hours, Mary 4 Hours TOTAL: 8 hours
Friday –> John 4 hours, Mary 4 Hours TOTAL: 8 hours
GRAND TOTAL: 40 hours
To conclude, if you want to get those three Options do not add additional Resource from Task Form Screen!
Regards!
Reblogged this on ilias katsagounos and commented:
Exceptional post and very helpful!!!
Thank you Mr Trajkovski!
Great article. How does Project Server timesheet behave in this case?
I didn’t try! I rere use PRoject Server 🙂