Material Resources with new Resource assigned to the Tasks in MS PROJECT 2016

Hi,

today I’m going to show you what is going to happen with Material resources when you assign additional Work resources to the Task which has already started and have some actuals. I will use Microsoft Project 2016!

First I’m going to create a single Task in my Project:

image

and two Work, and one Material Resources:

image

Now I am going to use Task Form, an I will assign John to the Task, and 100 Bricks as well. I will use in upper part of the screen Task Usage View, and I will show Actuals on the right part of the Screen:

image

and, after I click on the OK button, I will get:

image

Now, let’s say, that we are at the end of Day 2 and everything went well, so John has spent 16 hours, and 40 bricks. I will put that in Actuals:

image

Again, after I click on the OK button I will get:

image

Now suppose that for some reason I need Mary to finish that Task, and the Task is not effort driven:

image

As you can see, Mary has to spend the same amount of hours as John has, e.g. 24 hours (three days), and they will have to spend 20 bricks per day. So everything looks fine. But, what if Mary has Day off, for example, at Wednesday, 4.11.2015?:

image

If I assign Mary to the Task now, I will get:

image

Because Mary has a day off, Duration is now 6 days, and that mean that the Rest of work will be done in 4 not 3 days! That means that the Rest of Material resource should be split among these  4 days, and it will be 60/4 days = 15 bricks per day!

What If I assign Mary but the Task is effort driven?

image

As you can see, remaining hours (40 Total work – 16 Actual work for John) is 24 hours. Task is effort driven so those hours will be split among John, and Mary (12 hours each of them). John will work 8 hours at Wednesday, and remaining 4 hours at Thursday. Mary has a day off at Wednesday, and she will work 8 hours at Thursday, and remaining 4 hours at Friday.

What about Material Resource, e.g. Brick? Since the new duration is 4,5 days, and actual duration is 2 days, it means that remaining duration is 2,5 days. Remaining Material Resource to spend is 60 Bricks, so it is 60 /2,5 = 24 bricks per day no matter who will work and how much per day. That means that at Wednesday and Thursday 24 bricks are going to be spend, and at Friday (half day), only 12 bricks are going to be spend.

So be careful when you assigning additional Work resources to Task which already has been started and have some actuals.

Regards!

Unknown's avatar

About Nenad Trajkovski

Location: Zagreb, Croatia Occupation: Project Manager Interests: Project Management and MS PROJECT He was born in Zagreb, Croatia at 1963. After completing his college he started working on projects in different business areas (banking, manufacturing, automotive industry, distribution, oil companies, etc.) developing and implementing ERP systems into different companies. He has got a lot of experience working with people in different business processes and also possesses great knowledge in information technologies and financial services. Today he works as a business consultant, adn Project Manager in PERPETUUM MOBILE d.o.o. Zagreb. He is a regular lecturer for Project Management in MS Innovation Center in Varaždin, Logosoft Sarajevo in Bosnia and Herzegovina and SEAVUS GROUP in Skopje Macedonia. He was named the best lecturer of WINDAYS 2008 while his lecture was also voted as the best. In addition, he was in TOP 10 lecturers at the MS SINERGY 2009 and MS VISIA 2009, 2010. Shares first place as the best lecturer of KulenDays 2009 and 2010 and PMI Conference 2009 in Zagreb. He is also a regular lecturer in the MS Community. He is a Certified Accountant and a PMP (Project Manager Professional) and a PMI-RMP (Risk Manager Professional), MCP, MCT, and Microsoft Certified Technical Specialist - Microsoft Project 2010. From 01.01.2012 awarded with MVP (Microsoft Most Valuable Proffesional - Microsoft Project)!
This entry was posted in MICROSOFT PROJECT, Microsoft Project 2013, Micsrosoft Project 2016, MS PROJECT 2010, PMI, PRoject Management and tagged . Bookmark the permalink.

Leave a comment