-
Recent Posts
Archives
Categories
Category Archives: Project for the Web
% complete and Driving Tasks is Microsoft Project for the Web
Hi, in one of my previous post I have explained Driving Tasks in Microsoft Project for the Web. Now I will show you how this effect Task which has % complete greater than zero. First, I will crate new Project: … Continue reading
How to create Calendar from Resource using Microsoft Project for the Web?
Hi, today I will show you how to create brand new Calendar using Resource work hours in Microsoft Project for the Web! First I will open Dynamics 365: and I will choose – Project: Now, Let’s say that Tim will … Continue reading
How to set Calendars for Resource in Microsoft Project for the Web!
Hi, today I sill show you how to set specific calendar and apply it to resources in Microsoft Project for the Web! First of all, calendar template should be created! I will not explain again how to di it, because … Continue reading
How to connect Microsoft Project for the Web with Teams?
Hi, Today I will show you how to connect Microsoft Project for the Web with teams. I already have a Team which is created from existing Group: Project for the Web Group. I will click on the + sign and: … Continue reading
Duration, Start, and Finish relationship with Tasks in Microsoft Project for the Web
Hi, Today I will show you relationship between Task Duration, Start and Finish date in Microsoft Project for the Web. First I will create a simple Project with one Task: A you can see, Duration Start, and Finish date are … Continue reading
Multiple Projects with the same name in Microsoft Project for the Web!
Hi! When I use Microsoft Project desktop Application, or PWA I can have multiple Projects with the same name, but in different location (Folders, sites, etc.). But, what about Microsoft Project for the Web? Let me create two Projects with … Continue reading
Group name and Project name in Microsoft Project for the Web
Hi, as you know, in Microsoft Project for the Web, before you can assign Resource to any Task, you must either create a new Group or use existing one. Let’s say that I want to create new one.: As you … Continue reading
How to copy Tasks or Project in Microsoft Project for the Web
Hi, Today I will show you how can we copy part of Project or the whole Project in Microsoft Project for the Web. First I will create a brand new Project: As you can see, I have schedule, and resources, … Continue reading
How to navigate through linked Tasks in Microsoft Project for the Web?
Hi, today I will show you how to easily jump between Tasks in Microsoft Project for the Web! First, I will create new Project: or in Timeline View: Now, I will choose Fifth Task, and I will open Detail Page … Continue reading
How to add additional comments to Tasks in Microsoft Project for the Web?
Hi, today I will show you how add a comment to a Task in Microsoft Project for the Web. I will use example from my last Post: Now I will choose Foundation, and I will open Detail screen: and I … Continue reading