Resource pool and subprojects in MS PROJECT 2013!
Hi, again one of my Blog readers has a problem: “I followed your instructions but I am running into a small issue. While my master project shows all the sub-projects and the attached resource pool in the resources sheet, when … Continue reading
Fixed Duration and effort driven Task in MS PROJECT 2013
Hi, My Blog Reader has a problem: “Just a question. When I assigned a task to Fixed Duration, WITH EFFORT DRIVEN I see that Project has calculated some of the resources to work 50% or 33%. How does that … Continue reading
Resource vs. Task Calendar in MS PROJECT 2013 – PART 2
Hi, If you red my previous Post, you learned how to create Task Calendar, and force Resource to work on it on weekend. Is there another way? Yes it is! Credits to my Blog Reader for this post. Let’s say … Continue reading
Resource vs. Task Calendar in MS PROJECT 2013
Hi, another question from my Blog reader: “How do you determine whether to create a task calendar or a resource calendar?For example I start off with setting up the project calendar as standard, and then I decide that a particular … Continue reading
How to force Successor to start next working day in MS PROJET 2013
Hi, as usual, I’ve got a question from one of my Blog Reader: “If I have two tasks, the second task’s predecessor is the first task, and the first task ends on 7/10, I’d like the second task to … Continue reading