Specific Resource overallocation during the day using MS PROJECT 2019
Hi, I have a question from my Blog reader: “I want to solve overallocation of R1, since it is assigned to Task1 and Task2. I want to divide the work of R1 between Task 1 and Task 2 to solve … Continue reading
Estimation in hours and Resource Assignments with Fixed work Tasks in MS Project 2019
Hi, very often Tasks are estimated by effort, not duration. And Tasks are fixed work type. Now the question is: “How many hours will each resource spend at the Task?” I will show that in MS PROJECT 2019.¸ Let’s say … Continue reading
Actual duration and Actual start “problem” in MS PROJECT 2019
Hi, I have a question from blog reader: “Hi Nenad, I would like to track the progress in the following scenario:Task A: 3,5 d durationTask B: 3 d duration with a constraint FS with task AProgress: Say that Task A … Continue reading
How to apply same filter on different tables in MS PROJECT 2019
Hi, today I will show you how to apply same filter only once, and use different tables in MS PROJECT 2019. First, I’m going to create a simple Project: and I will create Resources needed for the Project: Finally I … Continue reading
Actual duration vs. Actual Start and Actual Finish in MS PROJECT 2019
Hi, today I will show you a short tip about tracking progress in MS PROJECT 2019! Suppose this scenario: The Task has 0,5 days duration, and is supposed to be started and finished at 28.01.2019. Now let’s suppose that it … Continue reading
Changing Resource Calendars and Task Progress–Microsoft Project 2019
Hi, today I will show you what happens if you change Resource Calendar AFTER Task is in progress with MS PROJECT 2019. First I will create two simple Tasks: and two Resources: Now I will assign John to Task 1, … Continue reading
When to use Task Calendar in MS Project 2019
Hi, I have very good question form one Blog reader: “Hello Nenad. I found your website while trying to solve a very particular problem in MS Project. Unfortunately, I haven’t been able to find a solution and was hoping that … Continue reading
How to Delay Project in MS PROJECT 2019
Hi all, I have a question from one of my Blog readers: “The project I am involve in is using only material resources and the unit rate for each resource did not change through time. Currently the project has more … Continue reading
My upcoming webinar
Hi all, first of all I wish you a happy New Year. In this post I will not write about MS PROJECT, but I will invite you to join my webinar at MPUG: https://www.mpug.com/event/different-ways-to-track-project-progress-with-microsoft-project/ In this webinar I will explain … Continue reading
Duration and Resource with 0% units assigned–how are they connected
Hi, in April this year I wrote a blog post about Resource with assignment 0%–what is it?. Now I have a question Blog reader: “I am trying to use Resources with a 0% Max as a placeholder/generic resource allocation. When … Continue reading