Category Archives: MICROSOFT PROJECT 2019

Actual duration and Actual start “problem” in MS PROJECT 2019

Hi, I have a question from blog reader: “Hi Nenad, I would like to track the progress in the following scenario:Task A: 3,5 d durationTask B: 3 d duration with a constraint FS with task AProgress: Say that Task A … Continue reading

Posted in MICROSOFT PROJECT 2019 | Tagged , | Leave a comment

How to apply same filter on different tables in MS PROJECT 2019

Hi, today I will show you how to apply same filter only once, and use different tables in MS PROJECT 2019. First, I’m going to create a simple Project: and I will create Resources needed for the Project: Finally I … Continue reading

Posted in MICROSOFT PROJECT 2019 | Tagged , | Leave a comment

When to use Task Calendar in MS Project 2019

Hi, I have very good question form one Blog reader: “Hello Nenad. I found your website while trying to solve a very particular problem in MS Project. Unfortunately, I haven’t been able to find a solution and was hoping that … Continue reading

Posted in MICROSOFT PROJECT, MICROSOFT PROJECT 2019 | Tagged | Leave a comment

How to Delay Project in MS PROJECT 2019

Hi all, I have a question from one of my Blog readers: “The project I am involve in  is using only material resources and the unit rate for each resource did not change through time. Currently the project has more … Continue reading

Posted in MICROSOFT PROJECT, MICROSOFT PROJECT 2019, Micsrosoft Project 2016 | Tagged | Leave a comment