Category Archives: PMI

Adjusting Assignments in the Team Planner View

Hi, I will show you how you can easily adjust assignments and reschedule your tasks in the project. First I will add four tasks to my project and they will be in manually scheduled mode, and I will not schedule … Continue reading

Posted in Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , | Leave a comment

Resolving over allocation in MS PROJECT 2010

Hi, I have received request for help from one reader of my blog. The request is: “Hi,I’m trying to create a new schedule for 1 person. I’d like to find a way to use automatic scheduling that will fill the … Continue reading

Posted in Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , | 3 Comments

Task Relationships

There are four different task dependencies (relationships): Finish to Start (FS): The finish date of predecessor task determines the start date of the successor task Start to Start (SS): The start date of the predecessor task determines the start date … Continue reading

Posted in Microsoft PRoject 2010, PMI, PRoject Management | Tagged , , , , | 8 Comments

Customizing the Ribbon in MS PROJECT 2010–Part II

In this Blog I will make my own Tab, Groups and Commands. I will go to Backstage view: and then:   I will add a brand new Tab and I will call it “My Custom Tab” Now I have a … Continue reading

Posted in Microsoft PRoject 2010, MS PROJECT 2010, PMI | Tagged , , | Leave a comment

Customizing the Ribbon in MS PROJECT 2010

In this blog I will write about customizing the Ribbon. Let me start with an example. If you want to define your resources on a project you can do it on the View Tab: I will prefer that everything about … Continue reading

Posted in MS PROJECT 2010, PMI, PRoject Management | Tagged | Leave a comment

How to split tasks in MS PROJECT 2010

Hi, Suppose that you have a project with 5 tasks as is shown in the picture: Task 3 has a 3-day duration, and will start on Monday, 25.04.2011 and finish on Wednesday, 27.04.2011. What if your task can be done … Continue reading

Posted in Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , | 6 Comments

Assigning and removing resource to tasks–BUG

  In this blog I will show you a bug that I found when removing resource from the task First, I will add two resources to the Project: Then I will add two tasks to the Project with same duration … Continue reading

Posted in Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , | 2 Comments

Constraints and deadline in MS PROJECT

In this post I will write about constraints There are three types of constraints: Flexible constraints. This is a default type of constraint in MS PROJECT. It means that a task can start As Soon As Possible Semi-flexible constraints. A … Continue reading

Posted in Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | 22 Comments

LEAD, LAG, ELAPSED TIME AND START TIME IN SCHEDULING

This blog will be a short one. I am going to describe lead, lag, elapsed time, and start time in scheduling. Lag is waiting time. For example, if you are pouring the concrete you have to wait 2 days before … Continue reading

Posted in Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management, Uncategorized | 2 Comments

Scheduling problems in MS PROJECT 2010 – Part 2.

Today I will write about scheduling problems when you put the start and the end date for tasks into MS PROJECT. I WILL NOT write about constraints and limitation with this method (for example about flexible and hard constraints and … Continue reading

Posted in Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | 4 Comments