Monthly Archives: June 2011

Setting Up Overtime Pay Rates and Assigning Resource Overtime Hours

  Hi, I will explain how can you assign overtime hours and overtime Pay Rate to Resource in MS PROJECT 2010 First I will add TASK 1 with 5 days duration: Now I will add Mary as a resource with … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , , | 9 Comments

Setting Up Pay Rates to Apply at Different Times

Hi, I will explain how can you enter up pay rates for a resource to apply at different times in MS PROJECT 2010 Suppose that you have a Resource with name Mary. Mary is working on your project, and se … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , , | 6 Comments

Entering Multiple Pay Rates for a Resource

Hi, I will explain how can you Enter Multiple Pay Rates for a Resource in MS PROJECT 2010 Suppose that you have a Resource with name Mary. Mary is working on your project as a Project Manager, and as Consultant. … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , , | 1 Comment

Setting Up Resource Availability to Apply at Different Times–Part two

Hi, In this blog I will demonstrate how can you set up different resource Availability to the same resource in MS PROJECT 2010. I will repeat “setup” from my previous blog. First I will add two tasks. TASK 1 will … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , | Leave a comment

Setting Up Resource Availability to Apply at Different Times

Hi, In this blog I will demonstrate how can you set up different resource Availability to the same  resource in MS  PROJECT  2010. I will make “set up” for my examples. First I will add two tasks. TASK 1 will … Continue reading

Posted in MICROSOFT PROJECT, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , | 6 Comments

MS PROJECT 2010–Tracking Task Progress

  Hi, I will show you how can you track Task progress in MS PROJECT 2010 First I will add a Task with 3 days duration: Now I will save the Baseline (Baseline means “PLAN”) and then: Now I will … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , | 7 Comments

Linking manually and auto scheduled tasks

Hi, I will show you what happens when you link manually scheduled tasks and auto scheduled tasks in MS PROJECT 2010. First, I will enter four tasks in manually scheduled mode: Now I will link them. I will make Task … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , | 5 Comments

Manually scheduled tasks

Hi, in MS PROJECT 2010  manually scheduling is a new feature. You can see how the new added task will be scheduled here: You can change default settings from manually scheduled task to auto scheduled task: and then: If you … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , | Leave a comment