A Small issue with Team Planner and Resource Leveling in MS PROJECT 2013

This will be a short one. Again, my fellow MPV Eric Uyttewaal found a Bug in MS PROJECT 2013.

I will Crete two Tasks in MS PROJECT 2013:

image

and one Resource:

image

Finally I’ll assign this Resources to both Tasks:

image

As you can see, John is over allocated. Now I’m switching to the Team Planner View:

image

Everything is fine (see Over allocation with red lines). Now I’m going to Level Resources:

image

and I’ll get:

image

Still, everything is perfect. No I’m going to Undone last Action:

image

and I’m getting:

image

There are no red lines here.

Funny!

Regards,

Unknown's avatar

About Nenad Trajkovski

Location: Zagreb, Croatia Occupation: Project Manager Interests: Project Management and MS PROJECT He was born in Zagreb, Croatia at 1963. After completing his college he started working on projects in different business areas (banking, manufacturing, automotive industry, distribution, oil companies, etc.) developing and implementing ERP systems into different companies. He has got a lot of experience working with people in different business processes and also possesses great knowledge in information technologies and financial services. Today he works as a business consultant, adn Project Manager in PERPETUUM MOBILE d.o.o. Zagreb. He is a regular lecturer for Project Management in MS Innovation Center in Varaždin, Logosoft Sarajevo in Bosnia and Herzegovina and SEAVUS GROUP in Skopje Macedonia. He was named the best lecturer of WINDAYS 2008 while his lecture was also voted as the best. In addition, he was in TOP 10 lecturers at the MS SINERGY 2009 and MS VISIA 2009, 2010. Shares first place as the best lecturer of KulenDays 2009 and 2010 and PMI Conference 2009 in Zagreb. He is also a regular lecturer in the MS Community. He is a Certified Accountant and a PMP (Project Manager Professional) and a PMI-RMP (Risk Manager Professional), MCP, MCT, and Microsoft Certified Technical Specialist - Microsoft Project 2010. From 01.01.2012 awarded with MVP (Microsoft Most Valuable Proffesional - Microsoft Project)!
This entry was posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI and tagged , , . Bookmark the permalink.

2 Responses to A Small issue with Team Planner and Resource Leveling in MS PROJECT 2013

  1. Martin Gergov's avatar Martin Gergov says:

    Hi, Nenad,
    I’ve run across your blog looking for solution to a specific problem with MS Project Pro 2013. I installed the pro version yesterday especially to test the Team Planner view but it appear to be non active?! Do you think you know what could be wrong with my set up? I’ll appropriate any help.

    Best regards,

    m

    • Nenad Trajkovski's avatar Nenad Trajkovski says:

      I really do not knopw what is going on! If you have Project 2013 standard Version, than there in no Team Planner in it. In PRo version it is in it, and I didin’t see any problem with that ever!

Leave a reply to Nenad Trajkovski Cancel reply