Replacing Generic Resources with Human Resources and overallocation!

Hi, I’ve got a question from one of my Blog readers: “When I assign Generic Resource to a Task and then replace it with human resource how can I decrease availability of generic Resource?” I will show you that in … Continue reading

Posted in Microsoft Project 2013, Micsrosoft Project 2016, MS PROJECT 2010, MS PROJECT 2016, PMI, PRoject Management | Tagged , | 2 Comments

“Keep task on nearest working day when changing to automatically scheduled mode” option in MS PROJECT 2016

Hi, a lot of my Blog readers asked me about “keep task on nearest working day when changing to automatically scheduled mode” option in MS PROJECT! I will show you what is it, and how does it work in MS … Continue reading

Posted in MICROSOFT PROJECT, Microsoft Project 2013, MS PROJECT 2010, MS PROJECT 2016, PMI, PRoject Management | Tagged | Leave a comment

Fixed duration Task and Resource Calendar

Hi, today I will explain how is Work field Calculated when you have Fixed Duration Task Type, and Resource Calendar. Of, course I will use MS PROJECT 2016! First, as I always do, I will create new Project with a … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2016 | Tagged | Leave a comment

Extended duration when Successor has been started in MS PROJECT 2016

Hi, my Blog reader has a problem: “So what if we aren’t moving the project, just adding time to a task where a dependent task was able to start early. As an exampleTask A 10 daysTask B 2 daysTask C … Continue reading

Posted in MICROSOFT PROJECT, Microsoft Project 2013, Micsrosoft Project 2016, PMI, PRoject Management | Tagged | Leave a comment