Category Archives: MS PROJECT 2010
Attaching Project Documentation to MS PROJECT
Hi, MS Project can (also) serve as Project central repository. If you are not using MS SharePoint, you can attach Project document in a few different ways. First I will add two tasks to the project: I want to … Continue reading
Adjusting Assignments in The Team Planner View – Part 2.
Hi, I will show what you should pay attention to when you adjust assignments and reschedule your tasks in the project. First I will add four tasks to my project and they will be in automatic scheduled mode, and I … Continue reading
Adjusting Assignments in the Team Planner View
Hi, I will show you how you can easily adjust assignments and reschedule your tasks in the project. First I will add four tasks to my project and they will be in manually scheduled mode, and I will not schedule … Continue reading
Resolving over allocation in MS PROJECT 2010
Hi, I have received request for help from one reader of my blog. The request is: “Hi,I’m trying to create a new schedule for 1 person. I’d like to find a way to use automatic scheduling that will fill the … Continue reading
Customizing the Ribbon in MS PROJECT 2010–Part II
In this Blog I will make my own Tab, Groups and Commands. I will go to Backstage view: and then: I will add a brand new Tab and I will call it “My Custom Tab” Now I have a … Continue reading
Customizing the Ribbon in MS PROJECT 2010
In this blog I will write about customizing the Ribbon. Let me start with an example. If you want to define your resources on a project you can do it on the View Tab: I will prefer that everything about … Continue reading
How to split tasks in MS PROJECT 2010
Hi, Suppose that you have a project with 5 tasks as is shown in the picture: Task 3 has a 3-day duration, and will start on Monday, 25.04.2011 and finish on Wednesday, 27.04.2011. What if your task can be done … Continue reading
Inactiving tasks
A great new feature in MS PROJECT 2010 is Inactive task command. In previous versions if you had a task which you decided not to do (because you didn’t have resources, or simply you just didn’t need it) you had … Continue reading
Assigning and removing resource to tasks–BUG
In this blog I will show you a bug that I found when removing resource from the task First, I will add two resources to the Project: Then I will add two tasks to the Project with same duration … Continue reading
Constraints and deadline in MS PROJECT
In this post I will write about constraints There are three types of constraints: Flexible constraints. This is a default type of constraint in MS PROJECT. It means that a task can start As Soon As Possible Semi-flexible constraints. A … Continue reading