-
Recent Posts
Archives
Categories
Category Archives: Uncategorized
Microsoft Project 2013-what is new? Part 5
Hi I will show you one excellent Report in MS PROJECT 2013! First I will recall Project from my Last Post: I will show you cost Table: Now, I will run new Report, Cost Overview: and I will get: … Continue reading
Posted in Uncategorized
1 Comment
Task Types and how they affect the Schedule–Part 2
Hi, let’s go. First we will do a Setup! I will add two Tasks to my Project: I will make Paint the wall effort driven: Now I will add two Resource to the Project: John and Mary! I will … Continue reading
Posted in Uncategorized
Leave a comment
Assigning Resources to the Tasks, Step by Step!!! – Part 1
Hi, As I promised I am going to explain how to assign resources to the Task, and what happens when I add or remove additional resources to those tasks in MS PROJECT 2010. After that I will explain the … Continue reading
Develop a Scope for my Project! Is it easy or not?–PART 3
Hi, As I promised, I will write about naming conventions, milestones, scheduling, risks in our project, what do we have to know about our tasks, and I will (maybe in the next or some other post) explain calendars. In … Continue reading
Posted in Uncategorized
2 Comments
The VOTING IS OVER
Hi, You have made a decision! It is: To start with blog posts “from the beginning”, and manage one “fictitious” project from the beginning to the end with MS PROJECT 2010. I got a flu. But anyway, from tomorrow on, … Continue reading
Posted in Uncategorized
Leave a comment
WHAT DO YOU THINK AGAIN!!!!
Hi, I am REPOSTING my last post. I got some answers, but I will like to have some more! Deadline for decision is tomorrow, 21.07.2011. So PLEASE, be proactive “Instead of new blog post I have a question for you! … Continue reading
Posted in Uncategorized
Leave a comment
Scheduling problems in MS PROJECT 2010
One of the biggest problems in MS Project is to understand how to manage the time. A friend of mine told me that he is not using MS PROJECT because each time he would change the calendar or working time, … Continue reading
Posted in Uncategorized
57 Comments
LEAD, LAG, ELAPSED TIME AND START TIME IN SCHEDULING
This blog will be a short one. I am going to describe lead, lag, elapsed time, and start time in scheduling. Lag is waiting time. For example, if you are pouring the concrete you have to wait 2 days before … Continue reading
About work and cost type of resources and problems when assigning them to the task.
In this post I will write about work and cost type of resources and problems when assigning them to the task. There are three types of resources: Work resource. This type of resource includes people and equipment needed to complete … Continue reading