Tag Archives: Microsoft Project 2010

The “Wedding” Project! How to set up Calendars in MS PROJECT 2010, and why? – PART 4

  Hi, The last Calendar type in MS PROJECT 2010 is the Task Calendar. Remember this: If you have the Project Calendar, and the Resource Calendar (or Calendars), and the Task Calendar, TASK CALENDAR HAS PRECEDANCE! Why do you need … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , | 6 Comments

The “Wedding” Project! How to set up Calendars in MS PROJECT 2010, and why?–PART 3

  Hi, if you reed my last post you already know that we have set up our project calendar, and exceptions. Here they are: and: Working time was set as:   Now I will show you how painful MS PROJECT … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , | 3 Comments

Risks in Project! Importance of Risk Management!!–PART 3

  Hi, we have done Risk Identification, and after that, we have made Qualitative Risk Analysis. So we have Probability, Impact and Risk Exposure (or Risk Score) for our Risks. We have sorted our Risks in MS EXCEL by Risk … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , | 5 Comments

Risks in Project! Importance of Risk Management!!–PART 2

  Hi! After we have found the Risks in our Project, next step is to estimate the Risk Exposure for every risk. We must have “Probability and Impact Matrix”. Here is an example: or: Probability: 1 = (5 – 10%) … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , | 1 Comment

Risks in Project! Importance of Risk Management!!–PART 1

  Hi, as I promised, in this post I will start to write about Project Risks. PROJECT RISK IS ALWAYS IN A FUTURE. RISK IS AN UNCERTAIN EVENT OR CONDITION THAT, IF IT OCCURS, HAS AN EFFECT ON AT LEAST … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , , , | 1 Comment

Develop a Scope for my Project! Is it easy or not?–PART 2

  Hi, when you have tasks for your project, you have to arrange them. How? It’s up to you. The best approach, from my point of view is to make Phases. I will explain how can you arrange the Wedding … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , | Leave a comment

OK! We have the PROJECT!! “The Wedding”!!!

  Hi, as I promised, I will start with a fictitious project. In fact, I will make two Projects. First Project will be “The Wedding”, and after I finish with this one I will continue with the second Project, and … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , | 3 Comments

HELP ME! I’M IN TROUBLE –MS PROJECT 2010 DOESN’T WORK

Hi, as I promised, in this blog post I will explain Project Process Groups (according to PMI), and Knowledge Areas, and how suitable MS PROJECT 2010 is for those Process Groups and Knowledge Areas! Project Process Groups are: Initiating, Planning, … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , | 7 Comments

Starting a new Project

OK, we will start our fictitious Project. But first we have to know some basic things about Project, Project Management, Project Manager, etc. Do you know what the Project really is? According to PMI (www.pmi.org) “A project is a temporary … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , | 3 Comments

WHAT DO YOU THINK?

Hi, Instead of new blog post I have a question for you! I was thinking about this blog site. Until now I was writing some kind of “tips and tricks”! I pick up some subject (as it crossed my mind), … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , | 7 Comments