CREATING OWN BUDGET IN MS PROJECT 2010–PART 1
Hi, I will explain how to make and track your own Budget in MS PROJECT 2010! Suppose that you want to have a budget (in money) for each task, and that you want to track variance from the actual … Continue reading
Setting Up the Project Budget
Hi, I will try to explain how to put the Budget in your Project with MS PROJECT 2010. I will repeat part of my Post from 13.10.2011! First of all, when you have a Budget Resource, make sure that you … Continue reading
Task Types and how they affect the Schedule–Part 4
Hi, If you red my last posts, you have noticed that one part is missing. That is: “What does it has to do with effort, and non-effort driven tasks”. Well it does, when you add additional resources to those … Continue reading
Assigning Resources to the Tasks, Step by Step!!! – Part 2
Hi, I will continue with my last Post. I will add John to the Task1. As you can see, in the Work field there is 16 hours (2 days X 8 hours per day). I will now assign Mary … Continue reading
Assigning Resources to Tasks! What are we talking about!?
Hi, this one will be about Resources, but without MS PROJECT 2010! I promise that I will continue with MS PROJECT 2010 and resources tomorrow! Before I start I have to say: I have received more than 100 compliments … Continue reading
How to split the Tasks in MS PROJECT 2010, and why!
Hi, it is Friday, and this post will be a short one! Suppose that you have a project with 5 tasks as is shown in the picture: Task 3 has a 3-day duration, and will start on Monday, 25.04.2011 … Continue reading
How to Use the Team Planner to Assign Resources
Hi, This is Repost of my two old Posts, and I am doing that because it has to be explained again, since I am in the “ASSIGNING RESOURCE” posts, and it should be mentioned again! I will show you … Continue reading
Assigning Resources to Tasks! Assigning Work Resources to the Tasks
From this post I will start with “How to assign different type of resources to the Tasks”. With assigning work resources to the Task, you are answering the question: “WHO WILL PERFORM THE WORK”. From my previous post you … Continue reading
Setting Up Resources in MS PROJECT 2010– the story begins! How to import Resources from the Address book, and from the Excel template
Hi, in my last blog post I was finished the Scheduling! In my next posts, I will temporary forget my “Wedding Project”, and I will start to explain how to set up, and manage the Resources in MS PROJECT … Continue reading
The “Wedding” Project! Building the Schedule? – PART 1
Hi, I received very interest comment for my latest post: “Very refreshing. Having said that, I am sorry, but I do not give credence to your entire plan, all be it stimulating none the less. It seems to me that … Continue reading