Tag Archives: MS PROJECT

Setting Up Resource Availability to Apply at Different Times–Part two

Hi, In this blog I will demonstrate how can you set up different resource Availability to the same resource in MS PROJECT 2010. I will repeat “setup” from my previous blog. First I will add two tasks. TASK 1 will … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , | Leave a comment

Setting Up Resource Availability to Apply at Different Times

Hi, In this blog I will demonstrate how can you set up different resource Availability to the same  resource in MS  PROJECT  2010. I will make “set up” for my examples. First I will add two tasks. TASK 1 will … Continue reading

Posted in MICROSOFT PROJECT, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , | 6 Comments

Linking manually and auto scheduled tasks

Hi, I will show you what happens when you link manually scheduled tasks and auto scheduled tasks in MS PROJECT 2010. First, I will enter four tasks in manually scheduled mode: Now I will link them. I will make Task … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , | 5 Comments

Manually scheduled tasks

Hi, in MS PROJECT 2010  manually scheduling is a new feature. You can see how the new added task will be scheduled here: You can change default settings from manually scheduled task to auto scheduled task: and then: If you … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , | Leave a comment

Assigning Resources to the Recurring Task

  Hi, As I promised I will show you something that I consider as a bug, even though some books say that it is not a bug, but it is “like it is”!? First I will add two resources, John … Continue reading

Posted in Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , | 2 Comments

Adjusting Assignments in The Team Planner View – Part 2.

Hi, I will show what you should pay attention to when you adjust assignments and reschedule your tasks in the project. First I will add four tasks to my project and they will be in automatic scheduled mode, and I … Continue reading

Posted in Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , | Leave a comment

Resolving over allocation in MS PROJECT 2010

Hi, I have received request for help from one reader of my blog. The request is: “Hi,I’m trying to create a new schedule for 1 person. I’d like to find a way to use automatic scheduling that will fill the … Continue reading

Posted in Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , | 3 Comments

How to split tasks in MS PROJECT 2010

Hi, Suppose that you have a project with 5 tasks as is shown in the picture: Task 3 has a 3-day duration, and will start on Monday, 25.04.2011 and finish on Wednesday, 27.04.2011. What if your task can be done … Continue reading

Posted in Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , | 6 Comments