Overtime, Costs, and Fixed Duration in MS PROJECT 2013

Hi, I got this issue from my Blog Reader: “OK. I am entering in hours in overtime work field as the instructions note but when I view the cost table, only the regular hours are calculated in the cost. This … Continue reading

Posted in MICROSOFT PROJECT, Microsoft Project 2013, PRoject Management | Tagged , , | Leave a comment

Night Shift Calendar in MS PROJECT 2010 / 2013

  Hello, again one of my Blog reader is in trouble: “SIR, PLEASE HELP ME IN MAKING A NIGHT SHIFT CALENDER WITH A DETAIED EXAMPLE WITH A BREAK DUARTION 01:00 AM TO 02:00 AM AND THE START TIME OF THIS … Continue reading

Posted in Uncategorized | 3 Comments

How to get percentage of costs in MS PROJECT 2010 or 2013!

  Hi, my Blog reader have a problem! He want to know how much money did he spend and, he wants that in percentage of Baseline in MS PROJECT 2010. He had sent me his mpp file! Here it is: … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, PRoject Management | Tagged , , , | 4 Comments

Network diagram and diagonal lines in MS PROJECT 2010, and 2013!

  I have one question from my Blog Post reader, about Network Diagram in MS PROJECT 2010: “Hi! I´m from Argentina and I was reading your blog, It´s really interesting and was really helpful for me. Thanks very much! I … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI | Tagged , , | 1 Comment