Task Calendars and Lag in MS PROJECT 2013

Hi, today I will answer to this question: “You have 2 tasks which own different task calendars (Standard 5day and 7day calendar). They are connected FS and have a lag, lets say 5 days. Which calendar does the lag use?” … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, PMI, PRoject Management | Tagged , , , | 5 Comments

Departments and Projects in MS PROJECT 2010 – Part 2

  Hi, as you know from my last Post, I created Departments, and I have assigned to the Project Manager Projman2 two departments (SIR and SIC), and no department to Project Manager named Projman1. Now let’s suppose that Project Manager … Continue reading

Posted in Uncategorized | 2 Comments

Departments and Projects in MS PROJECT 2010 – Part 1

  Hi, today I am gong to show how are Departments connected with Projects in MS PROJECT SERVER 2010! First let me show you Departments in my Company: and than: and I will get: Now I am going to show … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project Server 2010, PMI, PRoject Management | Tagged , , | Leave a comment