% Complete vs. Finish Date in MS PROJECT 2013

Hi, here is another problem from one of my Blog readers: “Hi Nenad – allow me to give you an example of my problem. A task with a finish date of May 5/14 has a % complete of 25%. When … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , | 8 Comments

Resources and Durations – how are they linked in MS PROJECT 2013!

Hi, very good friend of mine has a problem: “Nenad, please help me. I want to have some Resources with different working hours (for Example, John 1 hour per day, Mary 2 hours per day), and when I assign Single … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, PMI, PRoject Management | Tagged , , , , , | 2 Comments

Adding new Resource on the Partial Finished Task in MS PROJECT 2013 – Part 2 of 2!

Hi, Today I’ll show another way of adding Resource after it is, for example, 40% Finished. first, I’ll show you pictures from my Previous Post, so I will create on simple Project in MS PROJECT 2013: and I will create … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010 | Tagged , , , | 3 Comments

Adding new Resource on the Partial Finished Task in MS PROJECT 2013 – Part 1 of 2!

Hi, I had a very good question from one of my Blog Readers: “Hi Nenad. Can you tell me what is going to  happen if I have one Resource on the Task, and that Task is finished, for example, 40%, … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010 | Tagged , , , | 1 Comment