Baseline for Subprojects in MS PROJECT 2013

Hi,

Today I’m going to explain how to set and see Baseline for Subprojects in MS PROJECT 2013, and how to see those Baselines in Master Project!

First I’m going to create two Brand new Projects with one Task:

image

and

image

After saving this two Projects I’m going to create Master Project:

image

and I’m going to import Subprojects:

image

After importing the Second Project I’ll get:

image

I’ll switch Table to Variance:

image

and I’’ get:

image

Now I will save the Baseline in Master Project:

image

and:

image

Finally I’ll get:

image

As you can see, there is a Baseline for Tasks in Master Project, and for summary Tasks in Subprojects, but there is no Baseline for Tasks in Subprojects. To get those I’ll save the baseline for each Subproject separately:

image

The Procedure of saving Baseline in Subprojects is same as ion Master Project so I’ll not waste time to show you a picture. After saving the Baseline in each Subprojects when I look at the Master Project I will see this:

image

Voila! I can see Baselines for Task in Subprojects!

Piece of cake!

Regards!

Unknown's avatar

About Nenad Trajkovski

Location: Zagreb, Croatia Occupation: Project Manager Interests: Project Management and MS PROJECT He was born in Zagreb, Croatia at 1963. After completing his college he started working on projects in different business areas (banking, manufacturing, automotive industry, distribution, oil companies, etc.) developing and implementing ERP systems into different companies. He has got a lot of experience working with people in different business processes and also possesses great knowledge in information technologies and financial services. Today he works as a business consultant, adn Project Manager in PERPETUUM MOBILE d.o.o. Zagreb. He is a regular lecturer for Project Management in MS Innovation Center in Varaždin, Logosoft Sarajevo in Bosnia and Herzegovina and SEAVUS GROUP in Skopje Macedonia. He was named the best lecturer of WINDAYS 2008 while his lecture was also voted as the best. In addition, he was in TOP 10 lecturers at the MS SINERGY 2009 and MS VISIA 2009, 2010. Shares first place as the best lecturer of KulenDays 2009 and 2010 and PMI Conference 2009 in Zagreb. He is also a regular lecturer in the MS Community. He is a Certified Accountant and a PMP (Project Manager Professional) and a PMI-RMP (Risk Manager Professional), MCP, MCT, and Microsoft Certified Technical Specialist - Microsoft Project 2010. From 01.01.2012 awarded with MVP (Microsoft Most Valuable Proffesional - Microsoft Project)!
This entry was posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, PMI, PRoject Management and tagged , , , , , . Bookmark the permalink.

3 Responses to Baseline for Subprojects in MS PROJECT 2013

  1. Charles's avatar Charles says:

    Unfortunately, this will not help me. I have multiple sub-projects and I wish to have all sub-project baseline dates unique. For example, Sub-project 1 will have a baseline on May1, 2018, sub-project 2 will have a baseline on July 1, 2018. I would not want to simply use baseline 1 for the second sub-project, baseline 2 for the 3rd sub-project…and so on. Each sub-project will begin on it’s own baseline, unique to the other sub-projects.
    Thank you

  2. Desiree Williams's avatar Desiree Williams says:

    Thanks for the info

  3. Brenna's avatar Brenna says:

    Awesome!! Thanks!

Leave a reply to Desiree Williams Cancel reply