Monthly Archives: June 2015

Project start time in MS Project 2013

Hi, I will show you what happens if you change default start time in MS PROJECT 2013, and how to get right Project Start date. First I will set Date format so I can see hours. Click on File Tab, … Continue reading

Posted in Microsoft Project 2013, MS PROJECT 2010 | Tagged , | 12 Comments

99% completed of whole Project and/or Tasks in MS PROJECT 2013

Hi, very often I receive question like: “My Task remains 99% completed, and I do not know why?”, or “All Tasks are 100% completed but the whole project is 99% completed. Why?” Hera are two most often reasons for that. … Continue reading

Posted in Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010 | Tagged , , | Leave a comment

Actual start and finish date with material Resources in MS PROJECT 2013! When it does make a sense, and when it does not!

Hi, in this Blog Post I will show you how to use Actual Start and Finish date with Material Resources in a proper way. Of course, using MS PROJECT 2013! First I’m going to create brand new Project: As you … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , , , | Leave a comment

Actuals on Summary Tasks in MS PROJECT 2013

Hi, today I will answer on may questions I’ve got from my Blog Readers, regarding to entering  % Complete, and Actual work in Summary Task, instead in Sub Tasks. I will do it in MS PROJECT 2013! As always, I’m … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010 | Tagged , , , | Leave a comment