Customized resource calendar and its effect on task duration in MS PROJECT 2016!

Hi, my blog reader has a question and I’m going to repro his scenario step by step, and answer the question using MS PROJECT 2016. First I will create a 5 day Task: There are 2 resources assigned to the … Continue reading

Posted in Micsrosoft Project 2016, MS PROJECT 2016, PMI, PRoject Management | Tagged , | Leave a comment

Fixed Duration Tasks and Resource availability in MS PROJECT 2016

Hi, today I will show you what happens wen you have Fixed Duration Tasks with Resources assigned to them, and those resource are unavailable at the specific time. I will use MS PROJECT 2016 First I will create simple Project … Continue reading

Posted in Micsrosoft Project 2016, PMI, PRoject Management | Tagged , , | 1 Comment

How to avoid unnecessary Resources in MS PROJECT 2016

Hi, as you may already know, you can put Resources in MS PROJECT in many different ways. Sometimes this is good, but sometimes it can be very annoying. I will show you one example with MS PROJECT 2016! First I’m … Continue reading

Posted in MS PROJECT 2016, PMI, PRoject Management | Tagged , , | Leave a comment

Project Manager, Manager, and Micromanagement

Hi, today I want to discuss with you about Micromanagement. What is Micromanagement anyway? It is a Management style whereby a Manager closely observes and/or controls the work of his/her subordinates or employees, or project team. Is it bad? YES! … Continue reading

Posted in PMI, PRoject Management | Tagged | 2 Comments

Predecessors, Successors and Task form in MS PROJECT 2016

Hi, How often do you have a large Project with lot of Tasks? Hundreds of them. And your schedule is very complicated. And then, suddenly you have to change something. Maybe relations within Tasks, maybe your timeline is too long, … Continue reading

Posted in Micsrosoft Project 2016, MS PROJECT 2016, PMI, PRoject Management | Tagged , , | Leave a comment

Junior Project Manager and expectations

Hi! How many times did you hear about job role called: JUNIOR PROJECT MANAGER? Friend of mine (who is very, very experienced Project Manager) always gets angry when he hear this. He says: “There is no such a thing like … Continue reading

Posted in PMI, PRoject Management | Tagged | Leave a comment

Project Management Task in MS PROJECT 2016

Hi, very often I hear a question like: “OK Nenad, you are explaining how to make a good schedule, and how to assign Resources properly to Tasks!. But what about Task which are impossible to plan upfront, like, for example, … Continue reading

Posted in MS PROJECT 2016, PMI, PRoject Management | Tagged | Leave a comment