Tag Archives: MS PROJECT 2010
How to get the right name for a PROJECT SUBPROJECT in MS PROJECT?
Hi, again, one question from my Blog Reader: “Please assist. When I insert a subproject (Title: Primary Heat Exchanger) into my Master Schedule, it inserts the project but doesn’t give it the same saved name in the Master Schedule. … Continue reading
Finish date and the problem in MS PROJECT 2010! Or not?
Hi guys, I have a question from one of my Blog readers: “Is it possible to see Finish Variance in working days instead of calendar days? e.g. If i completed my task on Monday, instead of Friday, i want to … Continue reading
Could not retrieve server initialization data error when connecting to MS PROJECT SERVER 2010 via MS PROJECT PROFESSIONAL 2010
Hi, I will show how to handle this error. I am working in regular domain in my company (Perpetuum). But, for testing purpose we made a testing domain called nt. I have Project Server Account created in Project Professional … Continue reading
Tracking in MS PROJECT SERVER 2010–Defining Time Reporting Periods
Hi, if you decide to track the Task progress via MS PROJECT SERVER 2010 timesheet than you have to define Time Reporting Periods. To do that go to Server Settings and then Time Reporting Periods: … Continue reading
Posted in Uncategorized
Tagged Microsoft Project 2010, MS PROJECT, MS PROJECT 2010, MS PROJECT SERVER 2010
Leave a comment
Managing User Accounts in MS PROJECT SERVER 2010
Hi, In this Post I will show you how to create Users in MS PROJECT SERVER 2010, using PWA! First I want to show you the difference between Users and Resources. When you create Resource in MS PROJECT PROFESSIONAL … Continue reading
Enterprise Resources in MS PROJECT PROFESSIONAL 2010
Hi, in this Post I will show you how to create/edit Enterprise Resource in MS PROJECT PROFESSIONAL 2010 for MS PROJECT SERVER 2010. First I will open the Resource Center from PWA: and I will get: I will choose myself … Continue reading
Critical path and elapsed days! How does it works?
Hi, I will show you different behavior in MS PROJECT 2010 in Critical Path when you have, and when you do not have Elapsed days in duration fields! Suppose that you have three Tasks and each of them has … Continue reading
Agile Project Management, Scrum, Kanban, XP, Waterfall and MS PROJECT–Part 2 of 2
Hi, As I promised, I will write about using or not using MS PROJECT in agile Projects (Scrum, Kanban, etc.). First thing first. What does the expert says? Some quotes: “The traditional way to build software, used by companies … Continue reading
Agile Project Management, Scrum, Kanban, XP, Waterfall and MS PROJECT–Part 1 of 2
Hi, in my next two Posts I will skip writing about how MS PROJECT 2010, and MS PROJECT SERVER 2010 work, their features etc. I will write about PROJECT MANAGEMENT methodologies, frameworks, nutshells or however you name them, and … Continue reading
Enterprise Resources in MS PROJECT SERVER 2010
Hi, In this Post I will show you how to create Enterprise Resources in MS PROJECT SERVER 2010, using PWA! First I want to show you the difference between Enterprise and Local Resources. Enterprise Resources are resources are in resource … Continue reading
Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project Server 2010, MS PROJECT 2010, PMI, PRoject Management
Tagged Microsoft Project 2010, Microsoft Project Server 2010, Microsoft Project Server 2010-Enterprise Resources, MS PROJECT, MS PROJECT 2010, PMI, Project Management