-
Recent Posts
Archives
Categories
Tag Archives: MS PROJECT – Resources
Assigning Resources to the Tasks, Step by Step!!! – Part 1
Hi, As I promised I am going to explain how to assign resources to the Task, and what happens when I add or remove additional resources to those tasks in MS PROJECT 2010. After that I will explain the … Continue reading
Assigning Resources to Tasks! What are we talking about!?
Hi, this one will be about Resources, but without MS PROJECT 2010! I promise that I will continue with MS PROJECT 2010 and resources tomorrow! Before I start I have to say: I have received more than 100 compliments … Continue reading
Assigning Material and Cost Resources in MS PROJECT 2010
Hi, In this post I will explain how to set up, and assign material resources in MS PROJECT 2010. First I will add three material resources in Resource Sheet: Now I will add two Tasks: O.K. Now, I will … Continue reading
How to prevent Resource Overallocations by using the Team Planner–WATCH OUT!
Hi, In MS PROJECT 2010 there is a feature which can automatically prevent Resource Overallocations. I will add two tasks and two resources to the project: and: Now I will assign them to both, Task 1 and Task 2: … Continue reading
Different Resources Types in MS PROJECT 2010 and what do you have to know about them!
What are RESOURCES in MS PROJECT 2010. Those are people (human resources), equipment (machines), material (bricks, oil, butter,..) and cost needed to perform the Task(s), and to reach the Project Goals and Objectives. There are three types of Resources … Continue reading