Total hours limit with multiple Projects using MS PROJECT
Hi, I have a question from one of my Blog readers “Thank you for all your advices which you share on blog. I have an issue where I would like in resource pool file calculate the total “booked” work hours … Continue reading
Posted in MS PROJECT 2016, PMI, PRoject Management
Tagged Microsoft Poject 2016 - Work, MS PROJECT
Leave a comment
Recording task progress ahead of schedule in MS PROJECT 2016
Hi, today I am going to clarify one important thing which bothers a lot of of my Blog readers. I will go step by step through example and explain them. First I’m going to build simple Project: Now I will … Continue reading
Posted in MS PROJECT 2016, PMI, PRoject Management
Tagged Micorosft Project 2016, Micorosft Project 2016 - Schedule
1 Comment
Calculate Variance in Working Days after setting another baseline in MS PROJECT 2016
Hi, I’ve got a question which is: “How do you calculate the working days in formulas when the baseline is not Baseline 0, and you need to see variance of that Baseline?” It’s easy and I’ll show you how with … Continue reading
Posted in MS PROJECT 2016, PMI, PRoject Management
Tagged Micorosft Project 2016, Micorosft Project 2016 - Schedule
1 Comment
Big or small Project – how to know which is which?
Hi, many times I heard talking about big and small Projects. Many companies have different procedures for them. Of course procedures are lightweight for small Projects, and heavy for big ones. But, I am not going to talk about different … Continue reading
Posted in Uncategorized
Leave a comment
Material resources over different time than workload in MS PROJECT 2016
Hi, I have interesting question from one of my Blog readers:”I am working with Engineering services provider. I have created my resource pool sheet. I have assigned my resources (Employees/Engineers) on different projects. These engineers use different tools (licenses etc.) … Continue reading
Customized resource calendar and its effect on task duration in MS PROJECT 2016!
Hi, my blog reader has a question and I’m going to repro his scenario step by step, and answer the question using MS PROJECT 2016. First I will create a 5 day Task: There are 2 resources assigned to the … Continue reading
It’s all about People!
Hi, as a Project Manager I red thousands and thousand articles about Project Management. I focused on tips “how to Manage Projects on right way, and how to get Projects done” and I found a lot of useful and helpful … Continue reading
Posted in Uncategorized
1 Comment
Fixed Duration Tasks and Resource availability in MS PROJECT 2016
Hi, today I will show you what happens wen you have Fixed Duration Tasks with Resources assigned to them, and those resource are unavailable at the specific time. I will use MS PROJECT 2016 First I will create simple Project … Continue reading
Project Management, Processes, Procedures and PMBoK
Hi, today I’m going to describe some problems with Processes and Procedures within Projects. First of all what is Process, and what is Procedure? A process is a set of activities that interact to achieve a result. A procedure is … Continue reading
Posted in Uncategorized
1 Comment
How to avoid unnecessary Resources in MS PROJECT 2016
Hi, as you may already know, you can put Resources in MS PROJECT in many different ways. Sometimes this is good, but sometimes it can be very annoying. I will show you one example with MS PROJECT 2016! First I’m … Continue reading