Location: Zagreb, Croatia Occupation: Project Manager Interests: Project Management and MS PROJECT He was born in Zagreb, Croatia at 1963. After completing his college he started working on projects in different business areas (banking, manufacturing, automotive industry, distribution, oil companies, etc.) developing and implementing ERP systems into different companies. He has got a lot of experience working with people in different business processes and also possesses great knowledge in information technologies and financial services. Today he works as a business consultant, adn Project Manager in PERPETUUM MOBILE d.o.o. Zagreb. He is a regular lecturer for Project Management in MS Innovation Center in Varaždin, Logosoft Sarajevo in Bosnia and Herzegovina and SEAVUS GROUP in Skopje Macedonia. He was named the best lecturer of WINDAYS 2008 while his lecture was also voted as the best. In addition, he was in TOP 10 lecturers at the MS SINERGY 2009 and MS VISIA 2009, 2010. Shares first place as the best lecturer of KulenDays 2009 and 2010 and PMI Conference 2009 in Zagreb. He is also a regular lecturer in the MS Community. He is a Certified Accountant and a PMP (Project Manager Professional) and a PMI-RMP (Risk Manager Professional), MCP, MCT, and Microsoft Certified Technical Specialist - Microsoft Project 2010. From 01.01.2012 awarded with MVP (Microsoft Most Valuable Proffesional - Microsoft Project)!

The “Wedding” Project! Building the Schedule? – PART 6 (YEAH! The LAST ONE)

  Hi, I will continue my last post! First, I will change the duration for the wedding night from 1hr to 12 hrs.: Now I will arrange my timescale: I want in middle Tier to have days: and in Bottom … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , , | 3 Comments

The “Wedding” Project! Building the Schedule? – PART 5 (we are almost at the finish)

  Hi, In my previous post I have explained that Task no 6: “Call the guests by phone to the wedding” is a Predecessor of lot of other Tasks. I will again apply a filter to see those task: Because … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , , | 4 Comments

The “Wedding” Project! Building the Schedule? – PART 4

  Hi, If you remember I had (and I still have) a problem with my “wedding” project. I set up a Wedding Saturday , and Wedding Sunday Task Calendars in MS PROJECT 2010. As I said many times before I … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , , , | 1 Comment

The “Wedding” Project! Building the Schedule? – PART 3

  Hi, In this blog post I will start to Create the schedule, and I will show you how can get in trouble when you do it. If you want to track this Blog post, and next few one, you … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , , , | 3 Comments

The “Wedding” Project! Building the Schedule? – PART 2

  Hi, this post might be very boring! Because I am using the “Wedding” project I will put duration for each and every task! There are 100 task and I had to explain why I put those duration for each … Continue reading

Posted in MICROSOFT PROJECT, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , , , | 1 Comment

The “Wedding” Project! Building the Schedule? – PART 1

Hi, I received very interest comment for my latest post: “Very refreshing. Having said that, I am sorry, but I do not give credence to your entire plan, all be it stimulating none the less. It seems to me that … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , | 2 Comments

MS PROJECT 2010–The “Wedding” Project. Sample!

  Hi, I forgot to mention. If you want to try to work on my “Wedding Project”, here is the link: http://dl.dropbox.com/u/35142216/The%20wedding.mpp, and you can download everything what was (and is) on the Blog.   Regards,

Posted in Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , | 6 Comments

The “Wedding” Project! How to set up Calendars in MS PROJECT 2010, and why? – PART 4

  Hi, The last Calendar type in MS PROJECT 2010 is the Task Calendar. Remember this: If you have the Project Calendar, and the Resource Calendar (or Calendars), and the Task Calendar, TASK CALENDAR HAS PRECEDANCE! Why do you need … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , | 6 Comments

The “Wedding” Project! How to set up Calendars in MS PROJECT 2010, and why?–PART 3

  Hi, if you reed my last post you already know that we have set up our project calendar, and exceptions. Here they are: and: Working time was set as:   Now I will show you how painful MS PROJECT … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , | 3 Comments

The “Wedding” Project! How to set up Calendars in MS PROJECT 2010, and why?–PART 2

  Hi, In my previous post I have explained how to use the Project Calendar, and how to make an exception (Vacation, New Year etc.). But what if you have different working times over the period. For example, our “Wedding” … Continue reading

Posted in MICROSOFT PROJECT, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , | Leave a comment