Location: Zagreb, Croatia Occupation: Project Manager Interests: Project Management and MS PROJECT He was born in Zagreb, Croatia at 1963. After completing his college he started working on projects in different business areas (banking, manufacturing, automotive industry, distribution, oil companies, etc.) developing and implementing ERP systems into different companies. He has got a lot of experience working with people in different business processes and also possesses great knowledge in information technologies and financial services. Today he works as a business consultant, adn Project Manager in PERPETUUM MOBILE d.o.o. Zagreb. He is a regular lecturer for Project Management in MS Innovation Center in Varaždin, Logosoft Sarajevo in Bosnia and Herzegovina and SEAVUS GROUP in Skopje Macedonia. He was named the best lecturer of WINDAYS 2008 while his lecture was also voted as the best. In addition, he was in TOP 10 lecturers at the MS SINERGY 2009 and MS VISIA 2009, 2010. Shares first place as the best lecturer of KulenDays 2009 and 2010 and PMI Conference 2009 in Zagreb. He is also a regular lecturer in the MS Community. He is a Certified Accountant and a PMP (Project Manager Professional) and a PMI-RMP (Risk Manager Professional), MCP, MCT, and Microsoft Certified Technical Specialist - Microsoft Project 2010. From 01.01.2012 awarded with MVP (Microsoft Most Valuable Proffesional - Microsoft Project)!

Setting Up Pay Rates to Apply at Different Times

Hi, I will explain how can you enter up pay rates for a resource to apply at different times in MS PROJECT 2010 Suppose that you have a Resource with name Mary. Mary is working on your project, and se … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , , | 6 Comments

Entering Multiple Pay Rates for a Resource

Hi, I will explain how can you Enter Multiple Pay Rates for a Resource in MS PROJECT 2010 Suppose that you have a Resource with name Mary. Mary is working on your project as a Project Manager, and as Consultant. … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , , | 1 Comment

Setting Up Resource Availability to Apply at Different Times–Part two

Hi, In this blog I will demonstrate how can you set up different resource Availability to the same resource in MS PROJECT 2010. I will repeat “setup” from my previous blog. First I will add two tasks. TASK 1 will … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , | Leave a comment

Setting Up Resource Availability to Apply at Different Times

Hi, In this blog I will demonstrate how can you set up different resource Availability to the same  resource in MS  PROJECT  2010. I will make “set up” for my examples. First I will add two tasks. TASK 1 will … Continue reading

Posted in MICROSOFT PROJECT, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , | 6 Comments

MS PROJECT 2010–Tracking Task Progress

  Hi, I will show you how can you track Task progress in MS PROJECT 2010 First I will add a Task with 3 days duration: Now I will save the Baseline (Baseline means “PLAN”) and then: Now I will … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , | 7 Comments

Linking manually and auto scheduled tasks

Hi, I will show you what happens when you link manually scheduled tasks and auto scheduled tasks in MS PROJECT 2010. First, I will enter four tasks in manually scheduled mode: Now I will link them. I will make Task … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , | 5 Comments

Manually scheduled tasks

Hi, in MS PROJECT 2010  manually scheduling is a new feature. You can see how the new added task will be scheduled here: You can change default settings from manually scheduled task to auto scheduled task: and then: If you … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , | Leave a comment

Assigning Resources to the Recurring Task

  Hi, As I promised I will show you something that I consider as a bug, even though some books say that it is not a bug, but it is “like it is”!? First I will add two resources, John … Continue reading

Posted in Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , | 2 Comments

Attaching Project Documentation to MS PROJECT

  Hi, MS Project can (also) serve as Project central repository. If you are not using MS SharePoint, you can attach Project document in a few different ways. First I will add two tasks to the project: I want to … Continue reading

Posted in Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , | 1 Comment

Adjusting Assignments in The Team Planner View – Part 2.

Hi, I will show what you should pay attention to when you adjust assignments and reschedule your tasks in the project. First I will add four tasks to my project and they will be in automatic scheduled mode, and I … Continue reading

Posted in Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , | Leave a comment