% Complete and Actual hours for particular Resource in MS PROJECT 2016
Hi, I got interesting question from one of my Blog Readers: “Nenad this is very helpful, however, how would you adjust the scenario where the Actual work by John (100%) and Tom (50%) who are two resources assigned to this … Continue reading
Milestone and Finish to Finish relationship in MS PROJECT 2016
Hi, I’ve got an interesting question form one of my blog reader. He’s got a problem. I will show you what kind of Problem does he has with MS PROJECT 2016! Firs I will create new Project: Everything looks perfect. … Continue reading
Is it possible to make a Project plan without Project Start Date in MS Project 2016!
Hi, I’ve got very interesting question from one of my blog readers: “Is it possible to create project plan without Start date, and the let MS PROJECT 2016 to calculate finish like t0 + ndays?” I will show you … Continue reading
Resource calendar vs. Task Calendar, and weekends in MDS PROJECT 2016
Hi, Again, I have a question from one of my Blog readers, which is related to my previous post: “Hi Nenad,¸ Thank you very mush. But can you please explain the following inconsistency in MSP behavior: If in the example … Continue reading
Resource Calendar and weekend!
Hi, Again, I have a question from one of my Blog readers: “Nenad, I’m new to MS Project and really appreciate information on this site. I have a question regarding your post “Resource vs. Task Calendar in MS PROJECT … Continue reading
Task 0 in MS PROJECT 2016
Hi, This post will be short, but very useful. I have a question from one of my Blog Readers: “Hi Nenad,I discovered hat my task number usually starts from 1 instead of 0.Kindly assist on this.” I will show … Continue reading
Work assigned to Tasks vs. Work assigned to resources and Task Types in MS PROJECT 2016
Hi. Today I will show you what happens when you put work in hours to the Tasks, and then assign Resources to the Task, using MS PROJECT 2016. Firs II ‘m going to create new Project: As you can see, … Continue reading
How to calculate work, and then fix it in IN MS PROJECT 2016
Hi, friend of mine has a Specific problem. He wants MS PROJECT. I will show you this problem with MS PROJECT 2016! Project has one Task: Resources are: As you can see there are Workers with 800% capacity, Laborers with … Continue reading
Manually scheduled Tasks and Dependencies when changing Duration in MS PROJECT 2016!
Hi, today I’m going to show you what happens when you establish dependencies between manually scheduled Tasks in MS PROJECT 2016, and then change Duration. First I’m going create simple Project: Now I’m going to put Duration for each Task: … Continue reading
Replacing Generic Resources with Human Resources and overallocation!
Hi, I’ve got a question from one of my Blog readers: “When I assign Generic Resource to a Task and then replace it with human resource how can I decrease availability of generic Resource?” I will show you that in … Continue reading