Manually scheduled tasks

Hi, in MS PROJECT 2010  manually scheduling is a new feature. You can see how the new added task will be scheduled here: You can change default settings from manually scheduled task to auto scheduled task: and then: If you … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , | Leave a comment

Assigning Resources to the Recurring Task

  Hi, As I promised I will show you something that I consider as a bug, even though some books say that it is not a bug, but it is “like it is”!? First I will add two resources, John … Continue reading

Posted in Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , | 2 Comments

Attaching Project Documentation to MS PROJECT

  Hi, MS Project can (also) serve as Project central repository. If you are not using MS SharePoint, you can attach Project document in a few different ways. First I will add two tasks to the project: I want to … Continue reading

Posted in Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , | 1 Comment

Adjusting Assignments in the Team Planner View

Hi, I will show you how you can easily adjust assignments and reschedule your tasks in the project. First I will add four tasks to my project and they will be in manually scheduled mode, and I will not schedule … Continue reading

Posted in Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , | Leave a comment

Resolving over allocation in MS PROJECT 2010

Hi, I have received request for help from one reader of my blog. The request is: “Hi,I’m trying to create a new schedule for 1 person. I’d like to find a way to use automatic scheduling that will fill the … Continue reading

Posted in Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , | 3 Comments

Task Relationships

There are four different task dependencies (relationships): Finish to Start (FS): The finish date of predecessor task determines the start date of the successor task Start to Start (SS): The start date of the predecessor task determines the start date … Continue reading

Posted in Microsoft PRoject 2010, PMI, PRoject Management | Tagged , , , , | 8 Comments

Customizing the Ribbon in MS PROJECT 2010–Part II

In this Blog I will make my own Tab, Groups and Commands. I will go to Backstage view: and then:   I will add a brand new Tab and I will call it “My Custom Tab” Now I have a … Continue reading

Posted in Microsoft PRoject 2010, MS PROJECT 2010, PMI | Tagged , , | Leave a comment

Inactiving tasks

A great new feature in MS PROJECT 2010 is Inactive task command. In previous versions if you had a task which you decided not to do (because you didn’t have resources, or simply you just didn’t need it) you had … Continue reading

Posted in Microsoft PRoject 2010, MS PROJECT 2010, PRoject Management | Tagged , , | 2 Comments

Assigning and removing resource to tasks–BUG

  In this blog I will show you a bug that I found when removing resource from the task First, I will add two resources to the Project: Then I will add two tasks to the Project with same duration … Continue reading

Posted in Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , | 2 Comments