Tag Archives: MS PROJECT

Timeline View in MS PROJECT 2010

  Hi, one totally new feature in MS PROJECT 2010 is Timeline View! You can turn it on or off like this: What is it? Primary it is excellent Reporting tool. I will explain how to use it! I have … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , | Leave a comment

Workload without Resources in MS PROJECT– BUG OR NOT?

Hi, In this post I will show some “strange” behavior of MS PROJECT 2010 when I assign two resources to the effort driven, fixed duration Task! First, as always, set up! I will add two resources to the Project: Now … Continue reading →

Posted in MICROSOFT PROJECT, MS PROJECT 2010, MS PROJECT 20101, PMI, PRoject Management | Tagged , , , , | 2 Comments

Workload without Resources in MS PROJECT–what will happen?–PART 2 of 2

  Hi, in my previous Post I wrote about assigning resources to the Task when they already have workload. Now I will show what happens I f I add additional resource to the Tasks, regarding of Task Type in MS … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , , , | 1 Comment

How to get WBS (Work Breakdown Structure) from MS PROJECT 2010 to MS VISIO 2010

  Hi, I n my last post I had explained how to establish WBS in MS PROJECT 2010. But how to get WBS Diagram? You should MS VISIO 2010. Before that you must have Add In called: Visio Add-In for … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , , | 20 Comments

WBS (Work Breakdown Structure) in MS PROJECT 2010

  Hi, According to PMI (PMBOK 4th edition), WBS or Work Breakdown Structure is: “deliverable oriented hierarchical decomposition of the work to be executed by the project team to accomplish the project objectives and create the required deliverables, which each … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , , , | 14 Comments

Assignment Units VS. Peak Units in MS PROJECT 2010

Hi, as you know the Magic formula is DURATION * UNITS = WORK! But there is a change in MS PROJECT in representing this field. I made a setup for this Post! I have three Tasks, each of them has … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , , , | 1 Comment

Manually Scheduled Summary Tasks, and how to deal with them!

  Hi, I will show you how to deal with Manually Scheduled Summary Tasks in MS PROJECT 2010! As you already know Manually Scheduled Task are new feature in MS PROJECT 2010, and those tasks are fully controlled by you. … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , , | 2 Comments

Backstage in MS PROJECT 2010! What do we have here?

  Hi, in Backstage View in Microsoft Project 2010 you can setup many parameters for using MS PROJECT 2010. I will cover some of them, because if I want to cover them all, this Post will be very, very long. … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , | Leave a comment

How to track Actual overtime work in MS PROJECT 2010

  Hi, I received a question from one of my Blog reader: “After calculating the costing for work and overtime work, I baselined the task and then did tried to do the actuals in the task usage sheet. I did … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , , , | 1 Comment

How to create and use Templates in MS PROJECT 2010?

  Hi, You can use MS PROJECT 2010, for various Project types (software development, event organization, production, construction, etc.). For each new Project (of same type), you can build your task, schedule, resource pool, assignments, costs, reports, etc. fro the … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , , , | 4 Comments