-
Recent Posts
Archives
Categories
Category Archives: MS PROJECT 2010
Task Type in MS PROJECT 2013
Hi, again one question from my Blog Reader: “When looking at the Gantt chart with all my tasks it is hard to tell the difference between the tasks. Some as you described are for writing a document, some are for … Continue reading
How to apply different pay rates for Material Resources in MS PROJECT 2013?
Hi, again, my Blog reader has a problem: “Hi dearfirst I would like to say thanks for your above post, after that I would like to share one question with you which I have in mind, it is also … Continue reading
Calendars and Moving Tasks to non working days in MS PROJECT 2013!
Hi, again I have a question from my Blog Reader: “I liked your article and thought you may have an answer to a question I have.In Project 2010 with tasks set to Auto schedule if you schedule the start … Continue reading
How to assign 0$ costs for some Task with the same Resource in MS PROJECT 2013?
Hi, one of my Blog readers has a problem: “Good morning, Sir. I have a slight problem with my project. For some tasks the cost of one resource for tasks is 0$. We have the resource standard rate is … Continue reading
Network diagram and diagonal lines in MS PROJECT 2010, and 2013!
I have one question from my Blog Post reader, about Network Diagram in MS PROJECT 2010: “Hi! I´m from Argentina and I was reading your blog, It´s really interesting and was really helpful for me. Thanks very much! I … Continue reading
Units and Peak Units in MS PROJECT 2010! What are they?
Hi, I got this comment from one of my Blog readers: “I’ve seen there is a bug on calculation of USE!there are 2 conditions of fault: a) fixed work,,, you change duration… nothing happens to resource % useb) fixed Duration … Continue reading
Finish date and the problem in MS PROJECT 2010! Or not?
Hi guys, I have a question from one of my Blog readers: “Is it possible to see Finish Variance in working days instead of calendar days? e.g. If i completed my task on Monday, instead of Friday, i want to … Continue reading
Enterprise Resources in MS PROJECT PROFESSIONAL 2010
Hi, in this Post I will show you how to create/edit Enterprise Resource in MS PROJECT PROFESSIONAL 2010 for MS PROJECT SERVER 2010. First I will open the Resource Center from PWA: and I will get: I will choose myself … Continue reading
Critical path and elapsed days! How does it works?
Hi, I will show you different behavior in MS PROJECT 2010 in Critical Path when you have, and when you do not have Elapsed days in duration fields! Suppose that you have three Tasks and each of them has … Continue reading
Microsoft Project 2010 Scrum Solution starter
Hi, this will be the my shortest Blog Post! Since there are so many Articles in which you can read that MS PROJECT 2010 is not good as a Scrum tool, here is the link where you can find, … Continue reading